Remember this name-Navashino

Signed a protocol on the results of the first operational headquarters for the construction of Nizhny Novgorod NPP

  • 18.04.2012 16:30 

    The protocol was approved April 16, 2012 General Director of JSC "Concern Rosenergoatom" Evgeny Romanov (customer equipment) and the director of "NIAEP" — the management company ZAO NPP Valery Limarenko (Nizhny Novgorod NPP general designer and general contractor building the majority of nuclear power plants in Russia and abroad ).

    Under the agreements decided to start joint work with the government of the Nizhny Novgorod region to include the costs of development of the social sphere of the city Navashino in the Federal Target Program (FTP) for the development of the region.

 

 

 

 

 

 

      On the last image-trim from Navashino

In accordance with a decision in the near future will begin work on the design of the first stage of a station for the village of Nizhny Novgorod NPP construction. It is planned that construction of the village will be conducted in two stages: first — for 1200, the second — by 2600. In the village are provided in addition to residential and administrative buildings and structures of social and cultural sphere, providing comfortable accommodation.

To participate in the pre-construction and monitoring of the progress of construction of building customer units (JSC "Concern Rosenergoatom") in the III quarter of 2012 will be established Directorate for Construction of the Nizhny Novgorod NPP, which will operate in the region during the implementation period of the project.

Also decided to hold a client of the construction of public hearings to assess the environmental impact assessment (EIA) of the Nizhny Novgorod NPP. The hearing must be held before October 1, 2012.

Recall, the first staff meeting on the construction of the Nizhny Novgorod NPP held April 4, 2012. The main topic of discussion was the adaptation of the design of the station to the basic design of NPP "VVER-TOI."

In the work of the headquarters was attended by leaders of "Rosenergoatom" headed by the Director General Yevgeny Romanov, the experts of "NIAEP" — the management company ZAO NPP led by director Valery Limarenko, representatives of the government of the Nizhny Novgorod region, headed by Vice Governor, the first Deputy Chairman of the Government of the Nizhny Novgorod Region Vladimir Ivanov guide Navashino district.

 

Help Nizhny Novgorod NPP 
2011 
1. The Federal Service for Ecological, Technological and Nuclear Supervision (Rostekhnadzor) issued January 21, 2011 JSC "Concern Rosenergoatom" authorization to place units number 1 and number 2 nuclear power plant in Nizhny Novgorod Navashino district of Nizhny Novgorod region;

 
2. The Russian Government Decree № 1937-r of November 3, issued a consensus with the agencies and the government of the Nizhny Novgorod region offer the State Corporation "Rosatom" on the construction of the Nizhny Novgorod NPP with two power units installed capacity of each unit is not less than 1150 MW with the commissioning into service in 2019 and 2021, and as the location of the Nizhny Novgorod nuclear power plant in Navashino municipal district of Nizhny Novgorod region;

 
3. State Atomic Energy Corporation "Rosatom" has taken on December 8, the decision to peg the project "VVER-TOI" to the site of Nizhny Novgorod NPP.

 
VVER-TOI — a standard computerized design optimized high-power power plant based on the technology of pressurized water reactors VVER — enhances the safety and efficiency of the unit, and also reduces the costs of design, construction, operation, maintenance and decommissioning of the reactors. Fundamentals of VVER-TOI — AES-2006 with a maximum based on the experience gained in the development of industry organizations last NPP VVER technology projects (projects with RU-320, projects Novovoronezh NPP-2 NPP "Kudankulam", "Bushehr" NPP and NPP "Belene").

 
2012 
In accordance with the approved documents in 2011 to 2012 of "NIAEP" in Nizhny Novgorod NPP will complete the following work:

1. Start production of construction documents and materials to obtain a license for the construction of a nuclear power plant in Nizhny Novgorod variant "VVER-TOI" with the completion of the work in 2013.

 
2. Complete engineering research, infrastructure buildings and facilities on the construction site of Nizhny Novgorod NPP, a residential village of Power and linear objects in the surrounding area.

FAQ:

OAO Nizhny Novgorod Engineering Company "ATOMENERGOPROEKT" (JSC "NIAEP»), www.niaep.ru — Enterprise State Atomic Energy Corporation "Rosatom". One of the four engineering companies in the Russian nuclear industry. The company provides engineering services for the design and construction of nuclear power plants and reactors "turnkey".

The company is the developer of the most important objects of power in Russia. Nizhny Novgorod Engineering Company "AEP" today
serves as the general contractor for the construction of:
— Unit number 4 of the Kalinin nuclear power plant 
— Number of power units 3 and 4 of Rostov NPP 
— number of power units 1 and 2 of Baltic NPP; 
involved in the design of projects abroad: 
— Nuclear power plant in Kazakhstan 
— NPP "Kudankulam" in India 
— "Bushehr" NPP in Iran; 
conducts survey work to: 
— Units number 3 and 4 of Rostov NPP 
— Novovoronezh NPP-2 
— Tver NPP, 
— Nizhny Novgorod NPP. 

In late 2011, merged the competence of "NIAEP" and ZAO "ASE" (ASE). Package implemented integrated engineering company projects increased to 20 nuclear power units under construction at the same time in Russia and abroad. 

The company introduced modern methods of designing nuclear power plants and reactors using information technology. Since 2002, the design is based on a three-dimensional model of the object. 

E
stablished a quality management system that meets the requirements of international standards: it has been certified by the International Center TUV SUD.

Postscript. 

Could not help myself — I place a fun photo of the bridge across the Oka River, built 3 years ago and linked the Vladimir and Nizhny Novgorod region in Navashino. First there was a ferry crossing.

The bridge did not like? And it is a type of Far East bridges. 

 

      On the last image-trim from Navashino

In accordance with a decision in the near future will begin work on the design of the first stage of a station for the village of Nizhny Novgorod NPP construction. It is planned that construction of the village will be conducted in two stages: first — for 1200, the second — by 2600. In the village are provided in addition to residential and administrative buildings and structures of social and cultural sphere, providing comfortable accommodation.

To participate in the pre-construction and monitoring of the progress of construction of building customer units (JSC "Concern Rosenergoatom") in the III quarter of 2012 will be established Directorate for Construction of the Nizhny Novgorod NPP, which will operate in the region during the implementation period of the project.

Also decided to hold a client of the construction of public hearings to assess the environmental impact assessment (EIA) of the Nizhny Novgorod NPP. The hearing must be held before October 1, 2012.

Recall, the first staff meeting on the construction of the Nizhny Novgorod NPP held April 4, 2012. The main topic of discussion was the adaptation of the design of the station to the basic design of NPP "VVER-TOI."

In the work of the headquarters was attended by leaders of "Rosenergoatom" headed by the Director General Yevgeny Romanov, the experts of "NIAEP" — the management company ZAO NPP led by director Valery Limarenko, representatives of the government of the Nizhny Novgorod region, headed by Vice Governor, the first Deputy Chairman of the Government of the Nizhny Novgorod Region Vladimir Ivanov guide Navashino district.

 

Help Nizhny Novgorod NPP 
2011 
1. The Federal Service for Ecological, Technological and Nuclear Supervision (Rostekhnadzor) issued January 21, 2011 JSC "Concern Rosenergoatom" authorization to place units number 1 and number 2 nuclear power plant in Nizhny Novgorod Navashino district of Nizhny Novgorod region;

 
2. The Russian Government Decree № 1937-r of November 3, issued a consensus with the agencies and the government of the Nizhny Novgorod region offer the State Corporation "Rosatom" on the construction of the Nizhny Novgorod NPP with two power units installed capacity of each unit is not less than 1150 MW with the commissioning into service in 2019 and 2021, and as the location of the Nizhny Novgorod nuclear power plant in Navashino municipal district of Nizhny Novgorod region;

 
3. State Atomic Energy Corporation "Rosatom" has taken on December 8, the decision to peg the project "VVER-TOI" to the site of Nizhny Novgorod NPP.

 
VVER-TOI — a standard computerized design optimized high-power power plant based on the technology of pressurized water reactors VVER — enhances the safety and efficiency of the unit, and also reduces the costs of design, construction, operation, maintenance and decommissioning of the reactors. Fundamentals of VVER-TOI — AES-2006 with a maximum based on the experience gained in the development of industry organizations last NPP VVER technology projects (projects with RU-320, projects Novovoronezh NPP-2 NPP "Kudankulam", "Bushehr" NPP and NPP "Belene").

 
2012 
In accordance with the approved documents in 2011 to 2012 of "NIAEP" in Nizhny Novgorod NPP will complete the following work:

1. Start production of construction documents and materials to obtain a license for the construction of a nuclear power plant in Nizhny Novgorod variant "VVER-TOI" with the completion of the work in 2013.

 
2. Complete engineering research, infrastructure buildings and facilities on the construction site of Nizhny Novgorod NPP, a residential village of Power and linear objects in the surrounding area.

FAQ:

OAO Nizhny Novgorod Engineering Company "ATOMENERGOPROEKT" (JSC "NIAEP»), www.niaep.ru — Enterprise State Atomic Energy Corporation "Rosatom". One of the four engineering companies in the Russian nuclear industry. The company provides engineering services for the design and construction of nuclear power plants and reactors "turnkey".

The company is the developer of the most important objects of power in Russia. Nizhny Novgorod Engineering Company "AEP" today
serves as the general contractor for the construction of:
— Unit number 4 of the Kalinin nuclear power plant 
— Number of power units 3 and 4 of Rostov NPP 
— number of power units 1 and 2 of Baltic NPP; 
involved in the design of projects abroad: 
— Nuclear power plant in Kazakhstan 
— NPP "Kudankulam" in India 
— "Bushehr" NPP in Iran; 
conducts survey work to: 
— Units number 3 and 4 of Rostov NPP 
— Novovoronezh NPP-2 
— Tver NPP, 
— Nizhny Novgorod NPP. 

In late 2011, merged the competence of "NIAEP" and ZAO "ASE" (ASE). Package implemented integrated engineering company projects increased to 20 nuclear power units under construction at the same time in Russia and abroad. 

The company introduced modern methods of designing nuclear power plants and reactors using information technology. Since 2002, the design is based on a three-dimensional model of the object. 

E
stablished a quality management system that meets the requirements of international standards: it has been certified by the International Center TUV SUD.

Postscript. 

Could not help myself — I place a fun photo of the bridge across the Oka River, built 3 years ago and linked the Vladimir and Nizhny Novgorod region in Navashino. First there was a ferry crossing.

The bridge did not like? And it is a type of Far East bridges. 

 

 

 

 

 

Like this post? Please share to your friends: