On the Troitsk GRES (Chelyabinsk region). Established the first column of the machine hall under construction unit number 10

  • On the Troitsk GRES (Chelyabinsk region). Established the first column of the machine hall under construction unit number 10

At the construction site of JSC "OGK-2" — Troitsk GRES made installation of the first column housing the turbine hall unit number 10. For rack mounting of the machine hall will need more than 3 million tons of steel.


It will house the turbine and generator coal block.
In parallel, there are works on installation of boiler room. Continuing concreting the barrel stack and cooling tower. Implemented device monolithic reinforced concrete frame administration building. Preparations of foundations and support structures desulphurization circulating pump station.

Preparing for the commissioning of the logistical warehouse — a complex of modern storage facilities, which will at times reduce the area for storage of inventory, ensuring the needs of the station.

 

At the site of the Troitsk GRES under the contract for supply of power (PDM) is building a CSP-660 MW. The project, implemented by the company in the energy-deficient Chelyabinsk region, is unique. In the Russian coal-fired power generation capacity of 660 MW will be the first time.

The branch of JSC "OGK-2" — Troitsk GRES — one of the most powerful base of suppliers of electricity in South Ural. The installed capacity of the Troitsk GRES is 2,059 MW. The main and reserve fuel is Ekibastuz coal.