The Sayano-Shushenskaya hydroelectric power station started shore spillway

The Sayano-Shushenskaya hydroelectric power station completed the construction of the shore spillway, the press service of "RusHydro".


 Photo source:r-19.ru

"As a result we have not just a new building, but the increased safety of the station, as well as people living downstream of Yenisei" — Said Russian Deputy Prime Minister Igor Sechin at the workshop, the theme of which have restoration work at the Sayano-Shushenskaya HPP.


 Photo source:r-19.ru

Construction of an additional shore spillway at the Sayano-Shushenskaya hydroelectric power station, which began in 2005, was dictated by the need to improve the reliability and safety of hydraulic structures of the station. Shore spillway is designed primarily for the passage of extreme floods and floods of rare occurrence. Assumes the use of the shore spillway and in some cases to skip the ordinary floods.

Acceptance in the operation of the shore spillway was preceded by pre-commissioning testing facilities, which took place from September 28 to October 1, 2011.

As part of the test, the phased opening of the segment gates at the entrance to the center pole of full disclosure (9.5 meters), providing transit through the water ready to use elements of the building: two tunnels, five-step drop and the discharge canal. The maximum cost of water pass through the shore spillway was 3,000 m3 / s. During the test was carried out continuous monitoring of the state of the shore spillway, the parameters pass costs through both the tunnel and the process of reshaping the shoreline diversion channel.