Reconstruction of the network control system was completed Kostromaenergo

The branch of JSC "IDGC of Center" — "Kostroma" opening the control point network control center after reconstruction with a translation in its new premises.

In the new network control center set up three main jobs for dispatchers Kostroma and Galich and Sharja management zones and two backup jobs. Dispatch center meets all modern standards. It is equipped with a system of collective display, consisting of ten video cubes in the room — automatic climate control system, ventilation. On the workstation displays all the information that comes with the facilities management — 35-110 kV.

Dispatcher real time process spots change equipment status voltage levels and loads. Organized primary and backup channels of communication and remote control with facilities management, and dispatch centers, operational and technology groups and subjects of RES electricity: Branch of OAO "UES" Kostroma RDU, substations Volga-Oka enterprise backbone electric grids and substations of the Northern Railway, heat substations -Generating Company (TGC-2).

The organization of the network control center in Kostromaenergo began in August 2006 with the implementation of the first phase of non-operational functions. One of the main requirements that determined the adoption of operational functions, was the presence of primary and backup channels of direct communication with the objects of management, organization transmission of telemetry information between control centers, network control center, and substations, as well as training of the operating personnel.

In November 2009, NCC took over the operational management of electric grid complex of the region. Since then newly established organization monitors the electric grids of 0.4 — 110 kV, providing control of power equipment and power lines. This has reduced the time to eliminate the technological failures in the power supply system in the region, as well as to increase the reliability of the electric grid complex. Center began to perform the control of the equipment in the amount of 12 110 kV, 37 kV overhead lines 35, 62 substations of 35-110 kV. The main task today — the termination of the schedule of the transition to the target model of operational and technological management in the branch to increase the manageability of equipment and reduce the time of the decision-making process for the elimination of violations and restoration of power supply to consumers. The transition to the target model of operational and technological management is scheduled for completion early in the third quarter of 2012.

"The benefits of the established system — rapid exchange of information. From how to work intelligently control staff, the reliability and continuity of power supply, "- said Deputy General Director — Director of JSC" IDGC of Center "-" Kostroma "Alexander Glebov.

In order to improve the quality of personnel in Kostromaenergo constantly drilled procedures for emergency response, switching production to withdraw in the repair and commissioning of the electrical equipment. All this ensures the reliability of the electric grid complex of the region and uninterrupted power supply to consumers.