Altai and Novosibirsk region joined the new road

August 22, put into service on the route area village Kersey (Novosibirsk region) — the border of the Altai Territory. According to experts, this road is of strategic importance. It is part of inter-regional transport corridor linking the Altai region, Omsk, Novosibirsk and Kemerovo region, and the Republic of Altai and Mongolia due to the M-52.

The projected area of construction of the road "and 118km / a" K-17p ", Kamen-na-Obi" in the section Kersey-oz. Altai Territory in Orda district of Novosibirsk region, length of 26.205 km, was divided into three launch complexes, including the construction of access roads to the three settlements and the construction of bridges over the river and creek Aleus Krutishka.

Construction of the first complex and the entrance to the s.Spirino — through a contractor of "Novosibirskavtodor" began in November 2010 and successfully completed in October 2011.

Construction of a second start-up complex and entrances to the village of Ust-Aleus — and to c. Antonovo own general contractor of "Novosibirskavtodor" began in January 2012 and successfully completed on 1 November 2012.

The third stage of construction, the length of which is — 6.55 km, by the contractual organization of "Novosibirskavtodor" began in December 2012.

The total cost of the three launch complexes made — 1735 563.35 thousand rubles. 