Two generator TVF-125 arrived at the Tom-

On the fourth block of Tom-Usinsk GRES (Kemerovo region) delivered stator hydrogen-cooled turbogenerator TVF-125-2U3.

This is the second car of NPO "Elsib", delivered to the station as part of the project "Modernization of the Tom-Usinsk Kuzbass GRES branch of" Kuzbassenergo ". Back in late 2012 the station has been sent to the turbogenerator TVF-125, the commissioning is planned for November 2013
According to the implementation of the "Siberian Generating Company" Agreements for provision of power (DP) at the Tom-Usinsk GRES be implemented technical re-equipment of power number 4 and number 5. Enter the two turbine units CT-120 in 2013-2014. will increase the installed capacity by 48 MW to 1320 MW.
Tom-is the leading thermal power plants in Western Siberia. 9 TPP units with a total installed capacity of 1,272 MW are intended to cover the base load Kuzbass energy.

Like this post? Please share to your friends: