Fourth Boguchan hydroelectric power plant was put into regular commercial operation

Hydraulic Unit number 4 Boguchan plant moved to full-time industrial applications. JSC "Boguchan power plant" has received permission Yenisei of the Federal Service for Ecological, Technological and Nuclear Supervision (Rostekhnadzor) on Approval for hydroelectric station number 4 with an installed capacity of 333 MW. The total design capacity of four existing units will be 1,332 MW.

 

The first three units with station number 1, 2 and 3 were put into operation on 27 November, and on December 1, 2012 the station began to supply the wholesale market. In the first ten days of

Continue reading Fourth Boguchan hydroelectric power plant was put into regular commercial operation

Construction of the ninth section of the complete power plant on Boguchan

 Photo source:krskstate.ru

Boguchan GES (BoHPP) completed the construction of the ninth section of the concrete of the dam, according to "RusHydro", on a par with OK "Rusal" leading completion of the station.

"The construction of a concrete dam BoHPP continued throughout the winter period 2010-2011, despite the steady construction area low temperatures (minus 32-40 degrees)," — said in a statement.

This is the fifth section of the station, built up to the top of a hydraulic structure (214 meters). The first was the 23rd section (completed in March 2010), followed by the twelfth (in July), on the

Continue reading Construction of the ninth section of the complete power plant on Boguchan

After 30 years, completed the construction of hydropower dams Boguchan

On Boguchan plant was put into the body of the dam last concrete. In practice this means that building, which lasted more than 30 years, completed. Now assemble the last hydroelectric power. By the new year promises to run the latest ninth car.

This event has passed unnoticed, but for all hydrobuilders it became iconic. In total, over three decades, the dam was put almost three million cubic meters of concrete — more than in the pyramid of Cheops. Now turn on the rockfill dam. 

"To bring it up to standard, as opposed to

Continue reading After 30 years, completed the construction of hydropower dams Boguchan

A rotor mounted hydraulic unit number 6 Boguchan plant

On Boguchan plant, intensive work on the installation of power equipment. In particular, a complex operation performed the installation of the largest and heaviest element hydraulic unit number 6 — the generator rotor, which weighs 950 tons, diameter greater than 14 m

Installation work at the hydroelectric number 1 and 2 Boguchan plant completed, hydraulic units prepared to conduct pre-commissioning tests. Of hydroelectric number 3 and 4 completed the installation of major equipment, is currently being assembled auxiliary systems: the GA number 3 completes installation of valves, pressure testing of pipelines, painting lines and supporting structures, the GA

Continue reading A rotor mounted hydraulic unit number 6 Boguchan plant

In Zelenogorsk (Krasnoyarsk Territory) completed the construction of the substation Kamal-1

Through her Boguchan hydro electric power will be supplied to businesses and residents in the home. They built a substation 2 years. All the while, workers toiled under stress — next working substation, built in 1960.

 Photo source:pmk-s.ru

Workers substation "Kamal-1" proudly display the work of the new equipment, most of it is made overseas and has no analogues in the Urals. Substation was built 2 years, now there are commissioning. This substation — one of the units of electric power scheme from Boguchan HPP. Via high-voltage power energy from it will go first to the substation "Angara",

Continue reading In Zelenogorsk (Krasnoyarsk Territory) completed the construction of the substation Kamal-1

The operation for delivery of the last batch of runners for the hydroelectric power plant Boguchan

The barge-platform with the last batch of heavy hydraulic turbine equipment made of OJSC "Power Machines", arrived at the destination — the cargo berth Boguchan hydropower plant on the Angara River. On board the barge impellers are designed for hydroelectric turbines number 8 and 9 Boguchan hydropower plants, which are in the Krasnoyarsk region of JSC "RusHydro" and OK "Rusal".

 Photo source:rushydro.ru

Loading impellers on board the ship "Volga-Baltic-246" was held on July 26 in St. Petersburg. 29 July after the completion of the consolidation of cargo and preparing to ship the long march "Volga-Balt-246" was released on

Continue reading The operation for delivery of the last batch of runners for the hydroelectric power plant Boguchan

Boguchan plant

Blogger russos visited the power plant under construction Boguchan.

 Photo source:russos.ru

Full photos from this big project can be found at his blog.

Power Machines produced last, ninth Boguchan for hydro power plant

OJSC "Power Machines" manufactured, tested and delivered to the customer last, ninth hydro generator, designed to Boguchan plant, construction of which is JSC "RusHydro" and OK "Rusal" lead in the Krasnoyarsk Territory. Only under the terms of contracts between the "Power Machines" and the partners in the project of building the station — "RusHydro" and OK "Rusal" in 2006 — 2007 years, "Power machines" provide for the design and manufacture of power plant Boguchan nine turbines and nine hydro-rated capacity of 333 MW each. The installed capacity of the plant, equipped with the equipment, will be 3000 MW, average

Continue reading Power Machines produced last, ninth Boguchan for hydro power plant

After 30 years, completed the construction of hydropower dams Boguchan

On Boguchan plant was put into the body of the dam last concrete. In practice this means that building, which lasted more than 30 years, completed. Now assemble the last hydroelectric power. By the new year promises to run the latest ninth car.

This event has passed unnoticed, but for all hydrobuilders it became iconic. In total, over three decades, the dam was put almost three million cubic meters of concrete — more than in the pyramid of Cheops. Now turn on the rockfill dam. 

"To bring it up to standard, as opposed to

Continue reading After 30 years, completed the construction of hydropower dams Boguchan

Construction of the ninth section of the complete power plant on Boguchan

 Photo source:krskstate.ru

Boguchan GES (BoHPP) completed the construction of the ninth section of the concrete of the dam, according to "RusHydro", on a par with OK "Rusal" leading completion of the station.

"The construction of a concrete dam BoHPP continued throughout the winter period 2010-2011, despite the steady construction area low temperatures (minus 32-40 degrees)," — said in a statement.

This is the fifth section of the station, built up to the top of a hydraulic structure (214 meters). The first was the 23rd section (completed in March 2010), followed by the twelfth (in July), on the

Continue reading Construction of the ninth section of the complete power plant on Boguchan