Electrozavod shipped for the unit of Novovoronezh NPP-2 equipment

Holding company "ELEKTROZAVOD" shipped to unit number 1 Novovoronezh NPP-2 (Voronezh region) block single-phase transformer ORDTS-533000/500 capacity of 533 MVA, 500 kV.

The unit was designed and manufactured at the production complex of "ELEKTROZAVOD" in Moscow and refers to the power equipment of the new generation of heavy-duty transformers for high voltage class, news agency INFOLine.   Novovoronezh NPP-2 is being built on the new NPP-2006 project. At the moment, is being built 2 units with a total capacity of 2400 MW in the future it is planned to build two more power.

Continue reading Electrozavod shipped for the unit of Novovoronezh NPP-2 equipment

Power Machines produced the first generator for the Leningrad NPP-2

JSC "Power Machines" manufactured and tested in the factory-speed turbine-generator capacity of 1,200 MW, designed for the first power Leningrad NPP-2 (LAES-2).

Preparation for the tests of the turbogenerator for Novovoronezh NPP-2

 Photo source:power-m.ru

Contracts to supply a set of basic equipment machine room for equipment under construction Novovoronezh NPP-2 (NV NPP-2) and Leningrad NPP-2 have been signed between the "Power Machines" and OAO "Atomenergoprom" in May 2008. The total contract value is more than 40 billion rubles.

NV NPP-2 and Leningrad NPP-2 — is the first nuclear power plant to be built in Russia "from

Continue reading Power Machines produced the first generator for the Leningrad NPP-2

Power Machines produced the first turbine for the Leningrad NPP-2

 Photo source:power-m.ru

September 28. OJSC "Power Machines" manufactured and factory tests conducted on barring gear high-speed turbine capacity of 1,200 MW, designed for the first power Leningrad NPP-2 (LAES-2). Contracts to supply a set of basic equipment to equip the machine room Novovoronezh NPP-2 (NV NPP-2) and Leningrad NPP-2 were signed between "Power Machines" and OAO "Atomenergoprom" in May 2008. The total contract value is more than 40 billion rubles. At each nuclear power plant will be built on two power units with VVER power capacity of 1,200 MW.

Earlier, in December 2010, "Power Machines" fabricated and

Continue reading Power Machines produced the first turbine for the Leningrad NPP-2

To Novovoronezh NPP-2 delivered the most powerful body in the Russian reactor

The main element for the first power station fused from St. Petersburg on the rivers, unloaded from the barge and transported to the construction site.

The reactor vessel, produced by JSC "Izhora Plants", weighs 330 tons — or, as the waterway, to deliver such a bulky goods entirely would be almost impossible. In total, the barge was towed 3,800 miles — the Neva, Ladoga and Onega lakes, the Volga-Baltic Canal, the Volga and the Don. The last part of the path already in the Voronezh region, was the most difficult: because of the shortage of rainfall

Continue reading To Novovoronezh NPP-2 delivered the most powerful body in the Russian reactor

Power Machines produced a unique high-speed turbine generator for Novovoronezh NPP-2

OJSC "Power Machines" has produced and successfully tested a unique high-speed turbine with a full water cooling capacity of 1,200 MW, designed for the first unit of Novovoronezh NPP-2 (NV NPP-2).

Speed steam turbines and turbo-generators with capacity of 1,200 MW of nuclear power — this new development "Power Machines", focused on a new generation of nuclear power units with enhanced reliability and security that are created in the Russian Federation in the framework of the "NPP-2006".

Turbine generators T3V-1200-2, which are designed and manufactured "Power Machines" for NV NPP-2 and Leningrad NPP-2 (LAES-2) are the

Continue reading Power Machines produced a unique high-speed turbine generator for Novovoronezh NPP-2

To Novovoronezh NPP-2 delivered transport gateway for the power number 1

To Novovoronezh NPP-2 (general designer and general contractor — JSC "AEP", Moscow) delivered a transport gateway for the unit number 1.

Transport gateway

Transportation equipment manufacturer (Volgodonsky branch of JSC "AEM technology", is a "Atomenergomash") in Semiluky was carried by water on the river Don. Total length was about 700 km.

The installation of equipment on HBO NPP-2 will begin in November: body gateway will be installed in the design position at the level of 26.3 meters of the reactor building of Unit.

 

Transport gateway is a cylindrical chamber, sealed,

Continue reading To Novovoronezh NPP-2 delivered transport gateway for the power number 1

Petrozavodskmash manufactured housing sets of steam generators for Novovoronezh NPP-2

«Petrozavodskmash" production site of JSC "AEM technology" (included in the Engineering Division AtomEnergoMash Rosatom) has shipped the last fourth of the steam generator enclosure kit cases for Novovoronezh NPP-2 (NV NPP-2).

Transportation of the body is carried by water steam. Petrozavodskmash from the pier on Lake Onega cargo on the ship went to Moscow, on his road to deliver Machine-Building Plant "ZIO-Podolsk" (also included in AtomEnergoMash). 

In production at Petrozavodskmash remain set of 4 blocks of steam generators for the Leningrad NPP-2, and 2 cases designed for the Baltic nuclear power plant.

Continue reading Petrozavodskmash manufactured housing sets of steam generators for Novovoronezh NPP-2

Electrozavod shipped for the unit of Novovoronezh NPP-2 equipment

Holding company "ELEKTROZAVOD" shipped to unit number 1 Novovoronezh NPP-2 (Voronezh region) block single-phase transformer ORDTS-533000/500 capacity of 533 MVA, 500 kV.

The unit was designed and manufactured at the production complex of "ELEKTROZAVOD" in Moscow and refers to the power equipment of the new generation of heavy-duty transformers for high voltage class, news agency INFOLine.   Novovoronezh NPP-2 is being built on the new NPP-2006 project. At the moment, is being built 2 units with a total capacity of 2400 MW in the future it is planned to build two more power.

Continue reading Electrozavod shipped for the unit of Novovoronezh NPP-2 equipment

Power Machines produced the last of the four turbines for the second unit of Leningrad NPP-2

OJSC "Power Machines" produce and test a high-speed steam turbine capacity of 1,200 MW. This is the last of the four turbines generating "Power Machines", to be installed at existing nuclear power plants in the Russian NPP-2006 project.

The turbine will be installed on the second power unit of the Leningrad NPP-2.

Contracts for supply of main equipment of the machine room for equipment Novovoronezh NPP-2 and Leningrad NPP-2 were signed between "Power Machines" and OAO "Atomenergoprom" in May 2008. At each nuclear power plant will be built on two power units with VVER power

Continue reading Power Machines produced the last of the four turbines for the second unit of Leningrad NPP-2

To Novovoronezh NPP-2 began delivery of containers for ECCS unit number 2

To Novovoronezh NPP-2 (general designer and general contractor — JSC "AEP", Moscow) delivered the first two tanks of the emergency core cooling system (ECCS) for the power number 2.

ECCS accumulator tank is a cylindrical vessel volume of 60 cubic meters and weighing about 80 tons. Containers are an integral part of the passive part cistemy emergency core cooling. The passive part is functioning without the involvement of staff and the use of external sources of supply. It includes accumulator tank 12 filled with an aqueous solution of boric acid. 

Accumulator tank installed in containment

Continue reading To Novovoronezh NPP-2 began delivery of containers for ECCS unit number 2