In the Altai region commissioned part of the road Zmeinogorsk — Rubcovsk

Renovation and repair of the road are made in the framework of the agreement on social and economic partnership between the Administration of Altai Krai, OOO "UMMC-Holding" and OAO "Siberia-Polymetal".

The road "Zmeinogorsk — Rubcovsk — The wolf — Michael — Keys — Kulunda — Burla — the border of the Novosibirsk region" stretching 488 km provides a transport link with the steppe zone of the Altai Territory and Novosibirsk region with access to federal highway A-349. The road allows you to organize transport between settlements Zmeinogorsk, Rubtsovskoe, Volchihinskogo and other areas of the Altai Territory.

In 2012, OOO "UMMC-Holding" has been allocated funds for the reconstruction of 8.4 km section of the road the next. The works were successfully carried out by specialists KGKU "Altayavtodor" and OAO "Siberia-Polymetal". As funds for reconstruction and capital repair area 8.4 km have been sent from the regional budget. As the contractors were SUE Rubtsovsk DSU-6 and ZAVYALOVSKY DAC-5.

Reconstruction of the road object was made in the period from May to October 2012. The work was done in shifts. Involved more than 100 dump trucks, 50 units of earth moving equipment. Total volume of displaced soil was 395.0 thousand cubic meters. m, laid rubble — 75.3 thousand cubic meters. m, 39.0 thousand tons of asphalt mix. Were installed 16 concrete pipes at two corrugated pipe radius of 3.75 m for the safety and convenience of the population are six Auto Pavilion.

Like this post? Please share to your friends: