The big building in the city of Samara. Review for 2011-13

I bring to your attention the review of the construction of a large-scale project near Samara, who leads JSC "Volgospetsstroy." This bridge crossing "Kirov". The project includes: technical category 1 road length of 10.88 km, 6 road and rail bridges and viaducts, 4 interchanges at different levels and 3 engineering structures under the highway.

The social significance of the project. The bridge Kirov will lead to more favorable for the formation of traffic on the road network and the conclusion of intra traffic flows on the periphery of the city — the bypass, relieve the federal highway M-5, providing free passage of transit transport.
Construction of the bridge Kirov will begin development of the city on the opposite bank r.Samara in the framework of the national project "Affordable and Comfortable Housing — to Russian citizens." Its construction will solve the problem of transport accessibility for residents p.Chernoreche and in the future — the owners of low-rise buildings of the territory.

 

April 2011.

The main road after the bridge over r.Samara

Bridge over r.Samara

Began construction of the center (of the channel) flight

The construction of the interchange at the PC 80

View of the bay 6-7 (Left Bank r.Samara)

Reinforcement plates in the roadway supports axes 6-7

May 2011.

The device supports ladder gatherings number 1 (horse side)

Reinforcement skirting boards carriageway flyover 1-4

Railway overpass on PC 74 90. Painting of the steel.

July 2011.

The device supports the walls of the cabinet number 7

Sand-wash

August 2011.

Installation of metal anchoring arrangement

Manufacturing and tension guys

September 2011.

Installation of the span of the axes supports 5-6

View of the bridge over the Chyornaya River and Small artificial structure on the PC 100.

View of the construction to link disparate areas on the PC 73, transport interchanges and major roads.

October 2011.

The device of asphalt concrete pavement roadway in support axes 1-4

Installation of m / c anchor arrangement

Facilities for communication device disconnected areas on the PC 108.

The main road. Strengthening of slopes material Incomat Flex.

December 2011.

Concreting of the roadway slab in support axes 5-6.

January 2012.

Strengthening the slopes of the cones with concrete slabs. Reliance number 7.

Removing the steel piles sheet piling.

March 2012.

View of the pylons towers № 5,6. Installation of barrier fencing in support axes 4-7.

Concrete pipe culvert device on PC2 64.24 Congress number 2.

April 2012.

Bridge over Chyornaya River. The device and the strengthening of regulatory structures on the op. № 1.

May 2012.

View of the main roads. Strengthening of earthen slopes Geomat

View of the highway overpass on the PC 73, the railway overpass on the PC 74 and the highway overpass on the PC 80.

August 2012.

View of the bridge over the Chyornaya River.

September 2012.

Bridge over r.Samara. Disposition of slopes and strengthening regulatory structures on the op. № 7.

Wastewater treatment plants at op. № 7. Strengthening the surface of Reno mattresses. The device of the walls of the box-like gabions.

The main road. The device embankment subgrade

The device drainage on main road in the area of automobile overpass on the PC 73.

View of the bridge over the river. Samara

The device on the asphalt pavement span.

View of the main highway. Strengthening of earthen slopes Geomat. Laying crushed stone base under the asphalt coating.

Highway 80 overpass on PC

View of the railway overpass on the PK74. Drive the train on the overpass.

Road overpass on the PC 73.

November 2012.

View of the highway overpass on the PC 80.

View of the bridge and through the Chyornaya River Road overpass on the PC 108.

December 2012.

View of the main road

The main road. Strengthening of slopes material Incomat Flex

Construction of the overpass on the road PK108.

View of the automobile overpass on PK80 and construction of the interchange at PK80 16.28

February 2013.

Installation of stair railing convergence.

The device of the transport interchange at PC1 76.74.

March 2013.

The device supports the dam number 1. Sealing sand.