In Yekaterinburg, commissioned a new building Sverdlovsk RDU

In Yekaterinburg, commissioned a new building control center branch of JSC "UES", "Regional power grid dispatching Sverdlovsk region" (Sverdlovsk RDU).

The new control center of OAO "UES" is constructed in the framework of the territorial investment project to build the infrastructure and technological re-equipment of the Sverdlovsk RDU. The main objective of the project — improving the reliability of the supervisory control grid of the Sverdlovsk region.

Since its inception in 2002 the Sverdlovsk RDU housed in rented premises of the building of JSC "TGC-9", which imposes restrictions on the development of the technological infrastructure of the supervisory control of the regional power grid, and did not meet the requirements of the "Regulation on the technical policy of OAO" UES ".

The implementation of the investment project started in September 2007, when the land was purchased and a 3-storey building in Yekaterinburg at the address. Dagestan, 1. The project provided its comprehensive reconstruction with increasing number of storeys of the building up to 4 floors. During 2008 — 2009 GG conducted survey work has been developed and approved construction documents. Construction of the new building of the dispatch center of Sverdlovsk RDU began in March 2011. For the half year construction and assembly work, set up physical infrastructure, technical equipment of buildings carried out by means of supervisory control.

The new control center power system control Sverdlovsk region has modern facilities of the supervisory control of electric power modes. In the dispatch room has an instrument panel on the basis of twenty-four video projection cubes BARCO, providing high volume, accuracy and timeliness of information displayed on the state of the power system of the Sverdlovsk region.

The dispatch center is equipped with an integrated security system and a system for monitoring the operation of engineering equipment. The reliability of the control room and data provide a fiber-optic lines. For a continuous and reliable supervisory control of the regional power system provides a guaranteed uninterrupted power supply from the independent power supply of all equipment and supervisory process control and automated management systems. The building of the Sverdlovsk RDU is designed and built with the specific activities of the branch clock.

For seminars and workshops to improve the skills of workers in the new control center of OAO "UES" has a personnel training center. Its capabilities allow not only the training of experts of the process unit and emergency response drills dispatchers Sverdlovsk RDU, but also cross-system training with the participation of the operational staff of electric power industry operating area of the branch.

Control of the operation of the regional power system of the new dispatch center will expand the observability of the current condition of facilities scheduling, operational managers to accelerate the adoption of decisions, be more effective planning and management regimes.

Translation functions of the supervisory control of Power Sverdlovsk region in the new building is scheduled for October 2012.