In Moscow, entered into two power substations operating practices Ochakovo and MSU

During the reconstruction of the power substation "Ochakovo" increased by a factor of 2, and its size reduced from 15 to 3 hectares. Renewed energy facility is equipped with fully complete switchgear gas-insulated switchgear (GIS), 500, 220 and 110 kV. GIS has several advantages compared with conventional equipment: small size, long life (50 years) with a minimum of maintenance, high reliability, environmental friendliness and safety. Today the capacity is 3650 MVA substation.


 Photo source:mos.ru

Just commissioned a new power station 110/20 kW "MSU" JSC "Moscow United Electric Grid." The substation will provide the connection of consumers and the city of federal significance, including housing and medical education complex number 2 MSU, residential and office space.


 Photo source:moesk.ru

110/20 kW "MSU" was built in 2010, it meets all modern requirements for substation installed two transformers of 80 MVA, voltage 110/20 kV.


 Photo source:moesk.ru

Together with Russian Energy Minister Sergei Shmatko said Moscow Mayor Sergei Sobyanii examined control panel "Ochakovo" while listening to a story on the distribution of power an electrical substation.


 Photo source:mos.ru

The substation, located in the west of Moscow, was built in 1952. The question of the reconstruction was long ago, and it started a comprehensive update of the framework agreement between the Government of Moscow and RAO "UES of Russia", and modernization took place without interrupting the power supply to consumers.


 Photo source:mos.ru

This is an important object in the power supply the city: station "Ochakovo" is part of the facilities of the Moscow energy ring (ring network power supply in Moscow). Now she receives and distributes power from the United Energy Center and CHP-25. Curiously, during the renovation of its capacity increased by 2 times, and the area that is now the substation was reduced from 15 to 3 hectares.

Then Sergei Shmatko and Sergei Sobyanin congratulated power engineers with their professional holiday. Moscow Mayor thanked for power engineers work around the clock to provide electricity to homes and businesses, and the capital of Russia.
"Despite the fact that in recent years, Moscow has added more than a million people, the reliability of electricity from it not decreased, but rather increased. In the next five years it is planned to introduce more than 20 large-scale power generation facilities, and a total investment of more than 200 billion rubles. I hope this program will be executed in full. "

Then Sergei Sobyanin and Sergei Shmatko also officially commissioned the electrical substation "MSU". Staff at the station received thanks and congratulations from the mayor of the capital.

"Congratulations to everyone — he said — first of all MSU, which received additional sources of development. Congratulations and residents who have received additional power to their homes, businesses that operate in the Western District, reliably provide electricity. "