JSC "Gazprom Salavat Neftehim"With the participation of OOO" Gazprom energy "to the end of 2013, plans to put into operation new power — combined cycle gas turbine (CCGT) 410 MW on the New Salavatskaya CHP — in the construction of the third stage of the station. This is stated in the Journal of Gazprom.

 

The project cost about 16.5 billion rubles.
carried out under the project financing and existing infrastructure Novo Salavatskaya CHP. The first current PGU-410 must issue to the network in the first half of 2014. The draft scheme of power exercises "Gazprom Energy."

Construction of the plant is out of the program contracts for supply of power (PDM). At present, Russian generating companies introduced a number of new power generation capacity, but almost all of these investment projects implemented in the framework of the PDM. According to them, the state guarantees to pay a higher tariff power units built within the Democratic Party, which enables the investor to recoup the costs incurred. The construction of a large generating facilities (over 100 MW), the Democratic Party is not secured, with the established rules of the game now on the electricity and power, in most cases it is unprofitable. Creating the third turn on the New Salavatskaya CHP Gazprom believes the biggest "nedepeemovskim" facility in Russia.

Novo Salavat CHP (NSTC) began work in 1966. After entering in 1981, the second phase was the largest CHP cogeneration plant in Bashkiria with an installed capacity of 570 MW. The station is part of the "Gazprom Neftekhim Salavat", which it acquired in 2008. The station supplies the "Gazprom Neftekhim Salavat" all produced heat, and power supply are carried out through the wholesale power market (ADEM). It is planned that the implementation of the third stage will increase the supply to the growing power and petrochemical plants to solve the problem of energy shortage in the region.

FAQ: (From different sources)

In 2012, the company "Gazprom Salavat Neftehim" started construction of PGU-410T in the third stage of LLC "Novo-Salavat CHP."

320-ton gas turbine generator was manufactured in accordance with a contract signed by "Gazprom Neftekhim Salavat" and the largest electrical engineering by Siemens for the construction of combined-cycle plant. In January 2013, he was taken in Salavat. Following the generator to the construction site will be delivered to 289-ton gas turbine and steam turbine generator weighing 176 tons.

Technical and economic parameters of the new power unit — one of the best in the world combined-cycle units and significantly outperformed the existing CHP Russia. A significant advantage of PGU-410T — low emissions. The efficiency of the PGU-410T will be more than 58%.

Commissioning will provide an opportunity to increase the efficiency of heat and electricity, will meet the needs of the company's energy with the construction and start-up of new industries.