DTEK has completed the reconstruction of block number 10 Luhansk TPP Eastenergo

 

The largest Ukrainian energy holding "DTEK" has completed commissioning of a 10-m Unit Luhansk TPP LLC "DTEK Eastenergo," the press service of the company on Thursday.

According to her, as a result of upgrading capacity of the unit has increased by 35 MW — up to 210 MW, three times the reduced dust emissions by 60% reduced emissions of sulfur oxides.

The service life of the unit facilities as a result of the modernization period not less than 15 years.

Power unit number 10 — the first in a row at the Luhansk TPP reconstruction of the past. A huge amount of work: the modernization of the boiler and turbine stages except Bauman and increase the height of the blades of the last stage, the generator stator is completely replaced with a new one. On the basis of wet scrubbers installed two-stage ash collection and distribution modern microprocessor control system globally replacing obsolete equipment instrumentation

Issuance of Inspection of State Architectural and Construction Control in Lugansk region of the certificate of completion of the reconstruction, commissioning and re-marking on the power unit of 210 MW is scheduled for October 15, 2012.

As reported, the National Commission for regulation of the energy sector (NERC), Sept. 13 increased the installed capacity "DTEK Eastenergo" to 15 MW — up to 4172 MW and 4152 MW.

The need for a correction has arisen in connection with the reconstruction and subsequent remarking unit number 8 Kurakhovskaya TPS, which operates the generating company.