Evraz has put into operation the mine Erunakovskaja-VIII»

February 26, Novokuznetsk, Kemerovo region of a ceremonial commissioning of the mine "Erunakovskaja-VIII» of «Juzhkuzbassugol" (included in "Evraz"). Built not just coal mining company, and the complex production and transportation fuels necessary environmental and social facilities.

In the construction and equipping of mine already invested 6 billion. Overall investment in the project will amount to more than 13 billion rubles. Purchased modern equipment of leading world and domestic manufacturers of mining equipment, including Bucyrus. Created more than 1.1 million jobs. Salary underground workers an average of 48 thousand rubles a month.

Its capacity to 2.5 million tons of coal a year the company reached as early as next year. Go to the current volume of coal company "JUzhkuzbassugol" it will add the fifth. However, now we are working to increase the capacity of the company to 4 million tons.

Tax payments by companies to the consolidated budget of the Kemerovo region in 2013 are planned in the amount of 116 million rubles, and in 2014, to reach design capacity — 844 million rubles.

 

All produce are 100-percent illumination. The mine is equipped with a video surveillance system of underground sewage and development faces, as well as all conveyor transport chains. All processes are automated.

The mine introduced multifunction positioning system and alerting personnel (Flexcom), which provides a centralized location control personnel mines.

For mine safety system was introduced gas protection «Davis Derby», which provides:
aerogas control of the mine atmosphere;
control ventilation of mine workings;
fire protection;
control and management of underground power supply;
control of the water supply.

"Erunakovskaja-VIII» — the only mine in the Kemerovo region, which has its own fire station.

The mine built a new generation of wastewater treatment facilities involving several stages of cleaning and disinfection of the mine and surface water discharged from the territory of industrial sites. Mine water will go through several stages of cleaning and disinfection.

In parallel with the critical infrastructure of the mine is built administrative and utility plant, which provides for a comfort miners: the spacious changing rooms and washing department, a cozy dining room, a modern health center, offers several treatments, physiotherapy, massage room. There is even a sauna and fotary where the miners will be able to receive "dose" of UV light.

By the beginning of 2014 is planned to complete the construction of loading and storage facility at the station "Kazankovskaya", which will remove almost all the coal produced at the mine by rail. Thus, in 2013 the construction of the mine "Erunakovskom-8" will add another 7.5 billion rubles.