Completed a key phase of the construction of floating nuclear power plant

In St. Petersburg, the Baltic Shipyard completed the next phase of construction of the floating power unit (FPU), the world's first floating nuclear heat and power plant (FNPP) "Academician Lomonosov", reportswww.regnum.rubased on the information of the press service of the shipyard.

Today, the facility held loading tanks metallovodnoy protection (MHF) for nuclear reactors.

As explained in the press service of the two 300-ton tank Mil made at the Baltic Shipyard, were immersed in the reactor compartment FPU floating crane "Demag" in the presence of the customer, "Rosenergoatom". Because of the difficult ice conditions on the Neva operation carried out in two stages.

"Installation of the tank cost center — is a milestone in the construction of the vessel with a nuclear power plant — the general director of the Baltic Plant Alexander Voznesensky. — As a joke our technologists, which account for more than a dozen of such products, after loading the tank ship, consider, almost built. "

Buck Mil is one of the key elements of the reactor facility. It performs three functions at once: the basement under the reactor shielding and cooling circuit.

HSE Construction started in 2008 and frozen in mid-2011 and was renewed in December 2012, when, after long negotiations, a contract was signed between "Baltic Shipyard — Shipbuilding" and the customer unit, "Rosenergoatom" concern.

Under the contract, the Baltic plant shall deliver HSE ready to be towed to site, 9 September 2016.

Recall that floating nuclear power station "Academician Lomonosov" — head design series mobile transportable units of low power, developed OKBM. II Africantov. Floating nuclear power plant power plant has a maximum electrical output of 70 MW and includes two KLT-40S. Expected home base of the first floating nuclear power plant — the Chukchi Pevek.