Finished the regular delivery of transformers for power plant

Thus ended a complex transport operation to deliver heavy and bulky equipment needed to recoverhydropower.

 

The complexity of operations for the delivery of transformers was the heavy weight of the transported equipment — Each transformer weighs 235 tons (compared to the turbine wheelSayano-Shushenskaya HPPhave a weight 145 tonnes).

Because of the destruction in May 2011, the bridge on the river. Abakan near the station Kamyshta (Khakassia) power transformers were delivered by rail to coal mine Izykhsky (p. Podsineye, Khakassia), where we constructed a special unloading area. Further movement of the equipment at the Sayano-Shushenskaya hydroelectric power station was carried out by road.

After the bridge was rebuilt, the opportunity to deliver transformer by rail directly to Mr. Sajanogorsk the base freight and warehouse operations HPP, and from there by road directly to the station.

There are other ways to deliver the equipment at Sayano-Shushenskaya HPP.

August 8, 2012 g at the dock Mainskaya plant, located downstream of Yenisei 21.5 km from the Sayano-completed for Chevre— A special device for reloading equipment for HPP, arriving by water from Mr. St. Petersburg.

During the crash August 17, 2009 Mr. Transformer power plant was partially damaged, after an analysis of its technical condition, it was decided it was fully replaced.

Only at the Sayano-Shushenskaya hydroelectric power station will be installed 15 new 1-phase transformers brand ORTS-533000/500 500 kV voltage class (3 on each unit that combines two hydraulic) madeZaporozhtransformator(Ukraine).

Recall thatZTR won one of the tendersthe supply of equipment for reconstructionSSHHPPand had to put 16 single-phase transformers 533 MVA 500 kV.

At present, the station has been established 9 of transformers, and the rest will be installed in 2013-2014 as the commissioning of newhydraulic unitsNow instead of working equipment not injured in the accident.

Another one transformer will be held in reserve.

Note that at the height of the summer holidays, the employees of Sayano-Shushenskaya hydroelectric power station in conjunction with the Station of children and youth tourism and excursions organized for photographers Borus g and g Sayanogorsk Abakan creative expedition to the waters of the Yenisei.

The result of a three-day exhibition of photographs of the alloy will Yenisei seasons.

Within 3 days of a catamaran 10 photographers floated along the Yenisei River — from the power plant to a Mainskaya. Kirov (Shushensky district), held rapids, admiring the coastal waters of the Yenisei area, stayed at a photocall.

At the end of the expedition the best photographs in the exhibition will include a traveling exhibition that will be presented to residents and guests of Mr. Sayanogorsk the eve of the Day of the Yenisei.

Yenisei River — one of the greatest rivers in the country — part of the 10 largest rivers in the world by area water basin occupies an important place in the life of the whole of Siberia.

On the initiative of the Russian Geographical Society was established ecological feast day of the Yenisei, which aims to draw the attention of the public, businesses, government agencies to the problems of the river, its importance for the regions of Siberia and Russia as a whole, as well as the importance of preserving for posterity the Yenisei.


Like this post? Please share to your friends: