Corporation "Ural Industrial — Ural Polar" completes the construction of external power supply pipeline PurPe — Samotlor.
Until the end of March will be completed the construction of two high-voltage power lines and two electrical substations of 110/10 kV. The next step will be the commissioning, which is scheduled for completion at the end of June 2011. The final commissioning of external power supply will be 1 August 2011.

Also, the corporation continues to the erection 6,175 square meters. meters decent housing in cities Nizhnevartovsk, the November and Gubkinskii.
In addition, to date, the "Ural Industrial — Ural Polar" after all the necessary preparatory work for the construction of a fire station PS-1 LPS "Samotlor". photo