KOTES presented the results of feasibility study of the Ussuri CHP

In RAO ES of the East was presented on the basis of the range of pre-work on the project "Construction of the Ussuri CHP." KOTES presented the results of a feasibility study of the construction of power plants and transmission lines from the Ussuri Plant to the border with China.

Currently, the heating is carried out at the expense of Ussuriysk boilers. Construction of the new power station will increase the share of district heating consumers Ussuriysk from more effective in comparison with the existing boilers, heat supply source, providing for co-generation of heat and electricity, as well as significantly improve the quality of heat.

Designers KOTES offered four options for the construction of power plants of various capacities, with different sets of main power equipment. Among the options — construction of two cogeneration units, as well as the construction of two cogeneration and two condensing units for electricity exports to China.

Maximum considered Ussuri CHP electrical capacity of 840 MW. Also, three options of building power lines.


Like this post? Please share to your friends: