Krasavinskaya CHP work in full capacity

Krasavinskaya combined heat and power installed capacity of 63.8 MW started working in full. This possibility is confirmed by the results of tests carried out in test mode at the end of March. CHP earned in full.

Connecting Krasavinskaya GT CHP to the grid of the branch of JSC "IDGC North-West" "Vologda" was achieved through the construction project RP-110 kV in the investment program of the branch.

Work power will further the development of the infrastructure of Veliky district and the whole of the Vologda region, and will help ensure reliable and uninterrupted power supply to consumers.