IDGC of Siberia marks a significant increase of the electrical connections

In 2012, the subsidiaries received 43,418 applications for grid connection capacity of 2 383.3 MVt.Rost compared to the year 2011 was 32%.

Of the total volume of calls — two thirds, or 31,510 units. — Are statements of individuals to join the objects of everyday life, this figure compared with 2011 increased by 117.9 MW.


The number of prisoners in the 2012 agreements with consumers totaled 37,102 units., Which is 32% more than in 2011. Including 28,141 contract to join awarded to individuals, which is 38% more than in 2011 year.

It is worth noting that when attached to the grid object individuals all costs related reconstruction and construction of new networks of JSC "IDGC of Siberia" takes over, the consumer makes only a nominal fee set by the regional Tariff Service, in the amount of 550 rubles.

In 2012 signed contracts for technological connection of a number of major projects in all regions of the company: a complex of residential houses in the district of the Krasnoyarsk Territory Yemelyanovsky capacity of 4 MW, multi-storey residential buildings in the city of Krasnoyarsk capacity of 22.1 MW, shopping and entertainment complex in Krasnoyarsk capacity of 4.3 MW, and fair administrative and administrative-hotel complex in Omsk 4 MW; Klyuchevskoi agricultural production in the rural village of Omsk region capacity of 4.8 MW, the objects of exploration and mining of polymetallic ores of Noyon-pathology in the capacity of the Trans-Baikal Territory 30 MW; mining complex "Alexander" with capacity of 10 MW, etc.

Total in 2012, the company IDGC of Siberia has provided technological connection to electric networks of 21,953 new customers in the 565.2 MW, of which 16 012 — objects domestic purposes: private houses, gardens, garages. Compared to the previous year, the number of connections increased by 1.5 times to 199.1 MW