Construction News: NPP-2

On September 7 the next operational headquarters for the construction of the Leningrad NPP-2. General designer and general contractor of Leningrad NPP-2 is of "SPbAEP."

At the headquarters of the results were announced the construction unit number 1 in August:

performed on the reactor building reinforcement overlap at the level of -1.25 to -0.10 meter mark, produced reinforcement inside the reactor containment with a mark of 1.25 to reach 8.00 meters;

on the building of the turbine, reinforcement and concreting of overlap at the level of -9.20 to -0.10 meter mark;

on the building of nuclear maintenance performed wall unit with a mark of -0.10 to 4.70 meter mark, and others;

shell cooling tower number one rose over the month by 30 meters — from 117 to 147 meters. In the coming days, the shell construction of the first tower is completed, its height is 150 meters. As scheduled the work was carried out in August, and other objects of Leningrad NPP-2.

Currently, construction is underway on 72 sites (at the first power in the work are 56, the second — 16). On-site work 127 units of construction equipment and machinery. The number of employees in the construction of NPP-2 — about 3,000 people.