New boiler to Arkhangelsk Pulp and Paper Mill

Corporation Metso Power Oy supplied by JSC "Arkhangelsk PPM" basic piece of equipment for the assembly of a new multi-fuel heat boiler for co-combustion of sewage sludge and wood wastes at CHPP-1. The cost of equipment — 693 million rubles.

The total investment to the auxiliary equipment, design work, and the new facilities will amount to 1.5 billion rubles.

Recall that the main objective of this project — further increasing energy independence plant by burning biomass in heat recovery boilers and as a result, receive an additional amount of own steam and electricity to reduce the energy consumption of a third-party.

After the installation of the recovery boiler at CHPP-1 in I quarter. 2014 additional profits by reducing costs amount to more than 216 million rubles a year.