Turboatom has signed the largest contract in the last 25 years


 Photo source:ukr-prom.com

December 21, 2011 "Turboatom" has concluded a contract for the manufacture and supply of steam turbine 1,100 MW to the condenser for the unit number 4 of Rostov NPP (Russia)

Turbine — "million of" a high competitive rates to the world requirements.

In accordance with its contractual obligations "Turboatom" will design, manufacture and supply of high-pressure cylinder, three-cylinder low-pressure regulation system and steam distribution, the oil supply system, condenser and other accessories.

In the manufacture of the equipment will apply new technology of welding rotor die casting parts, and will continue the modernization of machinery equipment factory.

Delivery times capacitor — July 2014, the turbines — March 2015

Manufacturing will take place at the agreed schedule for 2012-2014,., And shipment of individual nodes — in the years 2014-2015.

The total weight of the equipment is about 5000 tons

The term input unit number 4 of Rostov plant commissioning is scheduled for June 2017

The contract is worth over $ 100 million.

Rostov NPP power unit has 2 turbines with a capacity of 1,000 MW, made "Turboatom": block number 1 started up in 2001, the block number 2 — in 2010

With the start of the unit number 3 of Rostov nuclear power plant in 2014-2015. it will be the 19th-turbine "million of" made "Turboatom" and put into operation. Total to date successfully operating 18 similar turbines at nuclear power plants in Ukraine, Russia and Bulgaria (South Ukrainian, Zaporozhye, Kalinin, Balakovskaya, Rostov NPP Kozloduy NPP). These units are well established in the operation of the first turbine has worked about 200,000 hours. A distinctive feature of the 1000-1100 MW turbines — slow-moving performance (1500 rev / min), which provides a number of advantages in terms of efficiency, reliability, security, ease of use and maintainability.

Like this post? Please share to your friends: