Oka shipyard has put in ekspuatatsiyu two tankers project RST27 «VFTanker-16 and 17-VFTanker

April 29, 2013 Shipping Company "VF Tanker" (Managing Director Sergey Bryzgalov) decided to use the sixth and seventh serial tankers of "Volga-Don max" class project RST27 deadweight in the sea / river 7030/5428 tons of "VF Tanker — 16 "(building number 02706) and the" VF Tanker — 17 "(building number 02707).

 
Works — builder — Oka Shipyard (director Vladimir Kulikov).

Customer — shipping company "VFTanker" is a holding company VBTH, the majority shareholder of which is the international transport group Universal Cargo Logistics Holding, consolidating a number of Russian shipping, stevedoring and shipping companies.
 
RST27 project designed by the Marine Engineering Bureau.
 
Contract DWT 6980/5378 tons of the ship "VF Tanker — 11" was exceeded by 50 tons — in fact it was 7030/5428 tons. The rate on the tests was 11.7 knots.

In comparison with other projects MEB tanker RST27 new project has strengthened river function, increased by 716 tonnes deadweight in the river (when compared with the "Armada") at:
• Rugged housing (marine grade II or R2 district — the old classification MS);
• practically the same fuel consumption;
• maintaining high capacity cargo tanks.

Hull's theoretical forms are the product of the research work carried out by the Marine Engineering Bureau in cooperation with Digital Marine Technology in 2010, and established using methods of Computational Fluid Dynamics (CFD modeling).
 
Then the model of the future tanker was tested in experimental pool Central Research Institute. Acad. Krylov. The experiment was fully confirmed the theoretical results.
 
Like other tankers mixed swimming MEB, court RST27 project is used as a single means of movement and management of full-circle rudder rudder trunk of have developed, primenenyat freight submersible pumps, they have no longitudinal bulkhead in CL and set in the cargo tanks.
 
Vessels of RST27 meet the dimensions of the Volga-Don Canal and Volga — Baltic Way. Overall length of 140.85 m, width — 16.6 m, depth — 6.0 m Belong to tankers "Volga-Don max" class.
 
In the design takes into account the special requirements of Russian and international oil companies, additional environmental constraints class of Russian Maritime Register of Shipping "ECO PROJECT" (ECO-S).
 
RST27 craft project designed for the transportation of crude oil and petroleum products without restrictions for flash.
 
Capacity of six cargo tanks and two slop tanks of 8,100 cubic meters. m, deadweight — 7030 tons at draft 4.20 m, in the river draft of 3.60 m — 5428 tons, cruising speed — 10.5 knots.
 
Cargo system is designed for simultaneous transport of two types of cargo, cargo pump performance — 6 x 200 m³ / h. Has two auxiliary steam boiler capacity of 2.5 t / h
 
As the main engines are two medium-speed diesels to 1200 kW, operating on heavy fuel oil with a viscosity of IFO380. Thruster — 230 kW. The power plant consists of three diesel generators from 292 kW emergency diesel generator parking 136 kW.
 
Crew — 12 people, places — 14 + pilot.
 
Autonomy (in the sea / river) — 20/12 days.
 
RST27 craft project meets the requirements of the class of Russian Maritime Register of Shipping KM (*) Ice1 R2 AUT1-ICS OMBO VCS ECO-S Oil tanker (ESP).
 
Whole Plant to be built fifteen tankers project RST27.
 
Head (At Oka Shipyard) ship Project RST27 (building number 02701) "VF Tanker — 11" laid 20.10.11. The descent took place on 27.04.12. Rented 17/07/12.
The second ship Project RST27 "VF Tanker — 12" (building number 02702) laid 27.10.11. The descent took place on 01.06.12. Rented 17/08/12.
The third vessel Project RST27 "VF Tanker — 13" (building number 02703) laid 27.12.11. The descent took place on 28.07.12. Rented 25.09.12.
The fourth ship Project RST27 "VF Tanker — 14" (building number 02704) laid 20.01.12. The descent took place on 23.08.12. Rented 02/11/12.
The fifth ship Project RST27 "VF Tanker — 15" (building number 02705) laid 20.03.12. The descent took place on 04.10.12. Rented 04.12.12.
The sixth ship Project RST27 "VF Tanker — 16" (building number 02706) laid 23.05.12. The descent took place on 22.11.12. Rented 04/29/13.
The seventh ship Project RST27 "VF Tanker — 17" (building number 02707) laid 20.06.12. The descent took place on 08/02/13. Rented 04/29/13.
The eighth ship Project RST27 "VF Tanker — 18" (building number 02708) laid 03.09.12. The descent took place on 26.03.13.
The ninth ship Project RST27 "VF Tanker — 19" (building number 02709) laid 18.10.12. The descent took place on 25.04.13.
The tenth ship Project RST27 "VF Tanker — 20" (building number 02710) laid 30.11.12.

 

May 6 was released to sea trials tanker project RST27 «Designer Zhivotovskiy" built "Plant" Red Sormovo "(building number 02010) for the company" Volga-Balt-Tanker "

The lead ship of the project "VFTanker-1" (building number 02001) was laid down on 30.08.11. The descent took place on 17.02.12. Commissioned 05.05.12.
The second ship Project "VFTanker-2" (building number 02002) was laid down on 15.11.11. The descent took place on 14.04.12. Commissioned 23.05.12.
The third vessel Project "VFTanker-3" (building number 02003) was laid 03.10.11. The descent took place on 17.03.12. Commissioned 17.05.12.
The fourth ship Project "VFTanker-4" (building number 02004) was laid down on 20.12.11. The descent took place on 18.05.12. Commissioned 09.06.12.
The fifth ship Project "VFTanker-5" (building number 02005) was laid down on 15.12.11. The descent took place on 15.06.12. Commissioned 10.07.12.
The sixth ship Project "VFTanker-6" (building number 02006) was laid 28.02.12. The descent took place on 12.07.12. Commissioned 20.08.12.
The seventh ship Project "VFTanker-7" (building number 02007) was laid 30.03.12. The descent took place on 16.08.12. Commissioned 17.09.12.
The eighth ship Project "VFTanker-8" (building number 02008) was laid 30.04.12. The descent took place on 28/09/12. Commissioned 12.10.12.
The ninth ship Project "VFTanker-9" (building number 02009) was laid 08.06.12. The descent took place on 19.10.12. Commissioned 29.10.12
The tenth ship Project "Designer Zhivotovskiy" (building number 02010) was laid 31.07.12. The descent took place on 04/23/13.

 

Just on May 5 was launched on the first of two tankers built VLCC (Very Large Crude Carrier), ordered a group of Sovcomflot (SCF). SKF is one of the world leaders in the segments of product tankers and oil tankers sizes "Aframax" and "Suezmax". With the construction of two new tankers Svet and SCF Shanghai company enters into a new segment of the largest in terms of tonnage of ships — class VLCC (deadweight of 300 thousand tons), which provides the current development strategy of GFR. Vessels of this size organically complement the existing structure of the fleet of the Russian shipping company, which will increase the competitiveness of the SCF on the world tanker market.

Tanker Svet be adopted in the autumn of 2013. Technical management of tankers, including monitoring of their construction, conducted by experts "Novoship" (a part of SCF). Building of ships of this class in Russia at the moment can not be.

The ship is named in honor of the first Russian oil tanker "Light" deadweight 1700 tons. It was built in 1885 by order of the firm "Nobel Brothers" for the transportation of oil and kerosene for export — the Black Sea from Baku. The ship was 89.5 meters long and 11.6 meters wide, the rig was 240 square meters, and the maximum speed of the tanker sailing — 7.5 knots. In the first crew of the Black Sea tankers were 50 sailors. It is the "Light", which became the first in the history of the Russian tanker, laid the foundations of tradition merchant marine.http://www.scf-group.com/npage.aspx?did=103537 