Builders of the third bridge in Novosibirsk approached the dock coast

 

Joining reason the third bridge over the Ob River in Novosibirsk happen roughly in the middle of February.

Said during the meeting at the construction site of the object VAT Governor Vasily Yurchenko, assembly of steel structures, connecting the base of the bridge, completed in February 2013, despite the possible extreme cold.

According to him, the connection of the left and right banks (from the street. Vatutin to Bolshevik) — the most important point from a technological point of view, so the presentation of the visit and Transport Minister Maxim Sokolov.

Yurchenko said that the completion of the construction is well ahead of the contractual terms (September 2014 instead of November 2014).

"At the end of the year got the second half of the funding from the federal budget — 4,000,000,000 50,000,000 rubles., Enabling today, at the beginning of 2013, surely to come with the volume of finance", — said Vasily Yurchenko.

Thus, in 2014 will be only laying asphalt work on fencing, lighting and road conditions. By next year, on the third bridge is completed and the installation of the longest arch span in Russia, to begin installation of the arch builders plan in September 2013.

 