Completed ground and flight certification tests of the PS-90A2

The aircraft factory "Aviastar-SP" specialists of JSC "Aircraft Engine", JSC "Tupolev" and "Aviastar-SP" has successfully completed ground and flight certification tests of the PS-90A2 on a Tu-204-100B number 64048LL.

The tests were carried out at the airport "Ulyanovsk-East" in the period 21.09.09g. by 18.11.09g. Tu-204-100B 64048LL number one engine PS-90A2 № 93-03, set in the first power plant, and with a single PS-90A engine installed in the second power unit.

In carrying out the test program:
Completed all required ground work, including a "race" engines and 10 runs on the runway
— Completed all required ground work, including a test with lateral blowing from the AN-26, with "race" engine with the lateral component of the velocity "wind" up to 15 m / s and 4 jogging on the runway.
Completed all required flight operations, encompassing the 18 flights with total flying 83 hours 47 minutes

In accordance with the Act formalized the end of the test materials obtained enough evidence to process documentation in providing a certificate of type PS-90A2.

The Tu-204-100B number 64048LL referred to "Aviastar-SP" for improvements to bring them to standard