Completed the zero phase of the construction of the building the Trans-Baikal RDU

Ltd. "Vympelsetstroy" (GC "Vympel") has completed construction of the zero phase of the building control center Transbaikalian RDU. Construction Customer — Open Joint Stock Company "System Operator of the Unified Energy System".

According to the project of construction of Julia Yakupova, "works on removal of utilities from the construction site, as well as lightning protection, vibration protection, underground part of the building. Routed outside the utilities (water, sewer). In accordance with the schedule of works, work began on the construction of the ground part of the RDU. The works on the concrete frame of the building of the 1st floor. Completion of the entire skeleton of the building is scheduled to end in October 2013. "