Gazprom has begun filling the gas pipeline Bovanenko — Ukhta

"Gazprom" has finished pneumatic testing and started to fill with gas the first line of the gas pipeline system "Bovanenko — Ukhta." This process step is preceded by commissioning the gas pipeline.

"The work is on schedule. Filling the process gas is conducted simultaneously from two directions: from the north — with Bovanenkovskoye field, and from the south — from Ukhta of the Unified Gas Supply System. In the near future pipeline will be ready to go, "- said Deputy Chairman Vitaly Markelov.

The system of main gas pipelines (SMG) "Bovanenko — Ukhta" — two line transmission system to supply the Yamal gas to the Unified Gas Supply System of Russia. JMG Construction began in December 2008, welding and assembly work on the linear part of the first line stretching more than 1,240 km were completed in May 2012. At present, construction of the second line of the SMG and eight compressor stations on the main compressor station (CS) "Baidarata" LLC "Gazprom Transgaz Ukhta" being commissioned work "under pressure".

At the world’s northernmost compressor station (CS) "Baidarata" LLC "Gazprom Transgaz Ukhta" started taking over gas to fill the SMM "Bovanenko — Ukhta."

10 June 2012 at 12.50 in the Yamal peninsula — with fishing Bovanenkovskoye condensate field (from the point of connection between 0 (zero) kilometers of gas pipelines) to the 1st string MG "Bovanenko — Ukhta" before COP Baidarata started feeding gas to fill the gas trunkline system (GTS ) "Bovanenko — Ukhta."

OOO "Gazprom Transgaz Ukhta" — an organization that will operate the gas transmission system (GTS) "Bovanenko — Ukhta" and be responsible for the smooth and trouble-free operation of all of its facilities without exception.

OOO "Gazprom Transgaz Ukhta" — 100% subsidiary of OAO "Gazprom", carries out production activities in the North-West of the Russian Federation. The length of the main gas pipelines operated by the Company of "Gazprom Transgaz Ukhta" — more than 12,500 kilometers of single line. Transport of gas carried 14 LPUMG.

Since 2006, within the boundaries of OOO "Gazprom Transgaz Ukhta" is actively working on the implementation of major investment project "Yamal" — namely, the design and construction of the gas pipeline system "Bovanenko — Ukhta."

Technological scheme of the gas pipeline, the following parameters:

— volume of gas condensate field in the Bovanenkovskoye — 115 billion cubic meters a year;

— 2 gas pipeline diameter 1420mm. with a working pressure 11.8MPa, with a 4-stitching underwater passage through Baidarata lip of pipe diameter 1220mm.,

—  9 dvuhtsehovyh compressor stations,

The pipeline from 0km. (From the point of connection of gas condensate field in the fishery Bovanenkovskoye) to Wow is about 1100km.

Completion of the construction of the system in these parameters in accordance with the schedule approved by Gazprom — 2016.

Commissioning of the CMS Bovanenkovo — Ukhta will be phased in until 2016.