Gotsatlinskaya plant came on the turbine wheel

At the construction site of Gotsatlinskoy plant, which is being built on the river Avar Koisu in Dagestan, delivered rotor wheel and the turbine shaft.

The impeller diameter of 3.1 meters and a weight of 20.4 tons is central turbine, directly interacting with the water flow. At the power plant will be installed Gotsatlinskoy two Francis turbine with a capacity of 51 MW, operating at design head 71 m

Hydraulic turbines Gotsatlinskoy plant produced by the Kharkov "Turboatom". Earlier in the presence of the customer at the plant site were produced by checking the main dimensions and impeller trimming, equipment has ultrasonic and dye penetrant inspection, the results of which the parties have signed the act of acceptance. Transport wheels are produced by the railway station Kizilyurt where it was reloaded onto trucks and delivered to the construction site.

Are ongoing concrete work in the building Gotsatlinskoy HPP on trench service spillway weir and water intake, as well as finishing the approach tunnel number 3 to the operational tunnel.

Construction Gotsatlinskoy plant with capacity of 100 MW and annual output of 350 million kWh is from January 2007. Organizer of construction — of "Sulak HydroCascade" — 100% subsidiary of JSC "RusHydro".

When completed, the plant will be the fourth Gotsatlinskaya in power to Dagestan. Putting it into operation will significantly reduce the shortage of electricity in the power of Dagestan, which in 2011 amounted to 1.1 billion kWh

Gotsatlinskoy hydro facilities include pebbly dirt dam 68 m high, shore power house with two types of hydraulic, water-supply path, the service spillway, outlet channel.