November 29 the opening of the reconstructed road section Sajanogorsk — Mainskaya GES — Cheryomushki.


 Photo source:r-19.ru

Construction and installation work on the reconstruction of the object made from January 18, 2011. The total cost of the work amounted to 876.378 million rubles.

During the reconstruction of the bridges have been repaired 9, as well as the work done to increase their carrying capacity, replaced 19 culverts, utility relocation conducted and strengthening the carriageway sections of the road with a total length of 11.57 km.

At the moment, the reconstruction of this road is completed. There will be planned activities for road maintenance (patching, etc.), if necessary will be the reconstruction of the road segments where it is needed.

"It was necessary to ensure the delivery of heavy and oversized equipment to the restoration work at the Sayano-Shushenskaya HPP in certain terms, that this was due to work on reconstruction of the object. Despite the fact that the deadline has been postponed several times, however, the order we have done — equipment, impellers and transformers have been delivered in accordance with the established timetable. Also strengthened the roadway, on the road sections where required, installed barrier fences "- said the Minister of Transport and Road Management PX Alexander Yegorov.