In the Irkutsk region opened the reconstructed road section Ust-Orda — Wasp

Remodeled eight-kilometer road section Ust-Orda — Osa launched in early November 2012. Road … made with double-layer asphalt-paved roadbed width of 10 meters, the roadway — six. During the work, laid 80 tons of sand and gravel, 10 tons of gravel and 18 tons of asphalt.

The reconstruction of the highway Ust-Orda — Wasp company — the contractor has started in May. We started with the arrangement of the base near the village of Kulunkun. At its peak in the area worked to hundreds of experts, half a dozen excavators, three graders, three bulldozers, three paver, about three dozen trucks ..