Indastek experienced a 220 kV A key — Magdagachi

The group of companies "Indastek" completed test voltage overhead line (VL) 220 kV "key — Magdagachi" in the Amur region. Customer — branch of JSC "FGC UES" — MES East.
According to the Managing Director of the group of companies "Indastek" Andrew Lukianchenko: "The line stood under the working voltage of 24 hours, the next phase of construction — measures to introduce it into operation."
Construction of 220 kV "A key-Magdagachi" was launched at the end of last year. The length of the transmission line was 54.7 km. During the work, the reconstruction of outdoor switchgear (ORU) at the substations of 220 kV "key" and the SS 220 kV "Magdagachi" cut down 293 hectares of the glade, installed 197 feet. Electric Construction work was severely hampered by the abundance of wetland areas and flooded areas.
Commissioning of the power facility is an important step in the implementation of the program of measures to ensure the power output of the Zeya hydroelectric power stations, as well as increase network capacity in an easterly direction to improve the reliability of electricity supply grid Amur.
The group of companies "INDASTEK" — provides the whole range of design and construction of electric power facilities of any complexity on the whole territory of Russia. The rich experience of the construction electrical substations, overhead and cable transmission lines of different voltage class allows for high carry out a wide range of activities, from design, supply complete sets of equipment and materials to carry out the construction, installation and commissioning