Kashira steel plant and boiler construction has shipped equipment to Aksu TPP

"Kashira steel plant and boiler construction" has shipped 600 tons of power equipment to the Aksu TPP (formerly Ermakovskaya TPP) is a part of JSC "Eurasian Energy Corporation".

The share of power Aksu TPP (Kazakhstan), accounting for 16% of all electricity generated in Kazakhstan. As part of the planned modernization of power units at the Aksu TPP, from September to November 2011 in Kazakhstan delivered 600 tons of oversized equipment:

shipped in September 10 platforms and two gondola cars weighing 220 tons,
October 10 platforms weighing 227 tons,
November 10 platforms weighing 147 tons.

As a part of the party was transported economizers equipment weighing up to 25 tons of steam boiler units of SRC, outsized (H0200) whose weight ranges from 13 to 18 tons.

Under a contract with the "Kashira plant metal structures and boiler building" regular transportation of energy equipment in Kazakhstan company performs "Inkotek Cargo". According to the schedule, a month is shipped 10-12 cars. Thus, by the end of the year the volume of deliveries of equipment for Aksu TPP can reach 800 tons.

Under this contract the company "Inkotek Cargo" provides the hardware manufacturer "Kashirskoe steel plant and boiler construction" services on railway freight forwarding, retrieval and supply of rolling stock, the implementation of other related logistics operations.