Near Khabarovsk completed a key stage in the construction of

Road bridge over the flow Amur

Near Khabarovsk completed a key stage in the construction of a road bridge over the flow Amur. Experts Group "SK MOST" completed work on sliding span.

Rigid span korbchatogo section specifies a method for longitudinal sliding of the island with the help of hydraulic equipment. This work began in early 2013 and were carried out in stages. The last stage of sliding — installation area of 210 m — was held in extremely difficult conditions associated with floods in the Amur. Total length of the set span — 945 m total length of the bridge — 957 meters

At the moment the builders are preparing for the next process step. They will lower the superstructure of capital in support of the design position. Also, the specialists of "BUILD TRUST", which is a general contractor, works on painting the superstructure and bridge deck waterproofing device.

Denis Pylypenko, Sergey Sysoev / SK MOST Photo: Denis Pylypenko / SK MOST