On NOVOChEBOKSARSK CHP-3 delivered a 100-ton generator stator for the new turbine

The stator (ELSIB)


On NOVOChEBOKSARSK CHP-3 branch of Mari El and Chuvashia "TGC-5" (included in the Company IES ") delivered to the stator of the generator — one of the main parts of turbine PT-80 (100) -130 / 13 capacity of 80 MW.

Stator production NGO "ELSIB" JSC was delivered to the CHP from Novosibirsk on a special train platform. Unloading the impressive dimensions of the part — its length is more than 5 meters in diameter — almost 4 meters, and the weight of 102 tons — from platform-transporter was made directly on the construction site, in the boiler and turbine plant station.

Enter turbine is planned for the end of 2013. Implementation of the project of modernization with the installation of the turbine plant of the PT-80 (100) -130 / 13 will improve the reliability of power supply Novocheboxarsk. This project is a priority investment program IES-Holding. Investment contribution to the project for two years, is over $ 1 billion.To conduct this technical operation has been done a lot of preparatory work — check the technical condition of bridge crane in the turbine shop; prepared unloading area; given instruction to the staff involved in unloading; taken measures to increase safety, operational discipline and safety; stator on arrival at the station — designed to remove cells that hold the equipment on the platform.

Immediately she unloading heavy equipment was carried out by means of two overhead cranes.

"A particular challenge of this work gave that two crane operator had to act in perfect sync, fulfilling the commands — the head of the GSO — Chief Engineer of the project Izhevsk branch of JSC" TGC-5 "on the implementation of priority investment projects of Alexander Semakin. — To solve this problem possible — thanks to precise actions taken by staff stator has been successfully uploaded to the engine room of the station. "

The rotor of the generator — the main component of the generator set — weighing about 32 tons was delivered to NOVOChEBOKSARSK CHP-3 in August 2012. On the whole bulk of equipment at the present time is already at the station.

Now, the construction work is continuing on the construction of the foundation for the new turbine. In particular, the complete filling of the twelve pillars of the foundation, installation of steel structures designed for mounting pads and accessories. Also, work is underway on the open ground the transformer. The next milestone will be the installation of the top plate — in the future here, at around 12 meters, will be installation of the turbine.

Novocheboksarskaya heat-3 was put into commercial operation in December 1965 and today its installed heat capacity is 869 Gcal / h, electric — 350 MW. Combined heat and power is the sole source of heat in Novocheboxarsk.