On Novokuibyshev CHP-1 successfully completed comprehensive testing of new power Flint

Project CJSC "IES" and the Samara branch of "Volga TGC" will further improve the reliability of power supply of the city and solve the old problem of power shortages of local energy system.

Integrated tests are the final stage of commissioning of the main equipment of the power. In accordance with the approved test plan and new CHP unit for three days carrying the load, and then passed the tests required to work in different operating modes. At STU-200 has carried out the quality of installation, tested the settings and operation of automated control systems.
 
The new unit is part of the investment IES Holding. The project involves commissioning at Novokuibyshev CHP-1 unit total capacity of 231 MW, consisting of three gas turbines General Electric, three steam recovery boilers and auxiliary equipment IEG. It will then deactivate the obsolete generating station equipment.

Solemn input power facility MAWP value of 10.5 rubles. into commercial operation is planned in the near future, the press service of the IES-Holding.

Like this post? Please share to your friends: