On the construction of Baltic NPP will increase three times the amount of work

January 11 at the construction site of the Baltic NPP construction at Neman district, held its first meeting in the new year operational headquarters. It brought together representatives of JSC "Concern Rosenergoatom", the management of "NIAEP" (the general contractor for construction works), the Baltic NPP and subcontractors.

Building site of the Baltic NPP
Building site of the Baltic NPP

The participants discussed the progress on each of the objects and tasks for 2012.

Summing up the results of 2011, the first deputy director of "NIAEP" — director of the Baltic branch of Vyacheslav Makhonin in its report said that the plan was fulfilled by 102%, and construction and assembly work — by 104%. According to the program in 2012 provided the growth of the volume of work three times. Already in the first quarter will increase the number of workers of various professions involved in the construction, with 508 to 1,500.

He instructed each subcontractor to prepare a schedule of the labor force and by the end of this year to involve at least 3,000 people.

"Today, the number one task — to ensure quality execution of all nuclear facilities in accordance with the schedule of construction", — said V.Mahonin. However, he drew the attention of the leaders of sub-contractors engaged in the construction, the fact that people were provided with all the necessary and safe working conditions in the winter.

Currently, the construction of the Baltic Nuclear Power Plant employs 573 people, 487 of them — residents of the Kaliningrad region.

"All the necessary licenses and other permits for the construction of power unit number 1, we obtained", — said the director of the branch of "Rosenergoatom" "Directorate for Construction of Baltic NPP" Eugene Vlasenko. He said that by the beginning of the main period of work prepared all the productions of services, the necessary resources and as a result of tenders placed large orders for the purchase of necessary equipment. Part of it is already beginning to do.

For continuous monitoring of the construction site approved a new nuclear power plant complex group, said E.Vlasenko. It included representatives of the Department of Technological, Environmental and Nuclear Supervision in the Kaliningrad region and they are now, due to the increased responsibility of tasks that are directly subordinate to the Federal Service RTN.

The thematic focus for 2012 provides V.Mahonin emphasized that all project documentation, development of which is of "SP6AEP" came not less than one month before the planned commencement of works. It will also provide a clear implementation timetable

 