On the Dniester PSP mounted impeller hydraulic number 2

 

On the Dniester PSP mounted impeller second hydro.
This is uaenergy reported in the press service of the bank "Ukrhydroenergo."
The impeller is made by the Kharkov "Turboatom".

According to the press service Ukrhydroenergo, October 3, chaired by CEO Igor Orphans will hold a meeting next operational headquarters for the construction of the first stage of the Dniester PSP composed of three hydroelectric units.

In Ukrhydroenergo also reported that on September 27, a meeting of the working committee for filling the upper reservoir of the Dniester PSP. According to the approved "Program works to improve the normal water level (NWL) of the upper basin of the Dniester PSP to reach 229.5 m", September 30 began its practical implementation.

Identified four stages of this important manufacturing operation. The first stage — to raise the level of 220.5 m to 223.5 m mark of the second stage of the injection of the upper reservoir — from 223.5 m to 225.5 m third — from 225.5 m to 227.5 m fourth — with 227.5 m to 229.5 m

Recall first hydraulic unit capacity of 324 MW and 421 MW turbine in pumping mode was put into commercial operation in late 2010 Hydroelectric number 2 and number 3 will be put into commercial operation in 2014 and 2015. respectively.

According to the draft, the Dniester PSP will consist of 7-hydro units with total capacity of 2268 MW in generating mode and 2,947 MW — in the pump.

The main customer of the construction of the Dniester PSP is "Ukrhydroenergo." All equipment, much of which is unique and has no analogues in the world, produced by domestic machine builders, in particular, "Turboatom" GP "Electrotyazhmash" and JSC "ZTR".

Today, the construction of the Dniester PSP involved about two thousand home builders.

As reported, the total estimated cost of the first phase of the Dniester PSP composed of three hydroelectric units of 8,000,000,000 457.566 th. Of these 4,000,000,000 560,806,000 USD falls on own means "Ukrhydroenergo" 2,000,000,000 332,900,000 — for the loans 1,000,000,000 563,860,000 USD — at the expense of the state budget. As of January 1, 2013 the project was funded by more than 5 billion USD.

"Ukrhydroenergo" exploits all the major hydroelectric power stations, located in the Ukrainian regions of the Dnieper and Dniester. The total installed capacity of hydroelectric generation company is 5007.6 (actual — 5036 MW). 100% of the shares owned by the state, through the Ministry of Energy and Mines.

Fitting the wheel hydraulic unit number 2