opened the bridge over the river Pechenzhitsa
During the flood in the spring of 2012 the old wooden bridge crossing was flooded. As a result, the two municipalities’ Tolshmenskoe "and" Velikodvorskaya ", where about three thousand people were cut off from the district center.
Work on the construction of the new bridge began in mid-2012, in August signed a contract with the contractor. The cost of the work amounted to 83.2 million rubles. Financing facility was made due to the Road Fund area.