The Organizing Committee of the XXII Olympic and XI Paralympic Winter Games of 2014 got a new office in the Imereti Valley. Nine-storey office building with car parking in the underground part of a total area of 42,934 m2 have erected two years.
From 1 to 7 floors — housed offices, and on the top two floors of an office center will be VIP-apartments, offices and meeting rooms, designed for high-level managers. The building has a dining room and a multimedia center with four meeting rooms. During the Olympic Games in 2014 it will be located "Olympstroy" and the International Olympic Committee.
©
The general contractor and the designer of the project: JSC "Concern" Monarch ".
Customer — "Olimpstroy"
Developer — GC "Itera".
Originally planned to build a building area of 25,000 m², then 30,000 m², in the end the total area was about 43,000 m². The building has grown in height from the original project into two floors. Changed and the facade.
©
Further, retaining shape in plan, the building is changing.
©
©
March 2013
©
Office building project Organizing Committee marked the international environmental certification BREEAM for the use of eco-efficient solutions in the energy and water supplies, the use of environmentally safe materials.
After the Olympic Games since April 1, 2014 the object was supposed to rent out.
©
©
The main technical and economic indicators of the building:
- Land area of 1.5 hectares
- Built-up area 6900 m?
- Total building area 42,934 m?
- aboveground part of 33,371 m?
- underground part of 9023 m?