PATH completed the commissioning of the mini-mill Iron Ozone 32 (photo)

Pervouralsk New Pipe Plant (included in the company CTRP) completed the commissioning of the mini-mill "Iron Ozone 32".

The company completed the construction of CTRP-mill in November 2010. "Iron Ozone 32" — one of the largest investment projects in the domestic industry and the Sverdlovsk region. The volume of investments — about 19 billion rubles, of which about 1 billion was directed to an environmental dimension.

May 4, 2012 the head of the city district administration Pervoural’sk Yuri Pereversev signed authorization for commissioning electric arc PATH "Iron Ozone 32". 

The technologies used ESPK will produce steel billets for pipes manufactured in accordance with the most stringent national and international quality standards and deliver the products not only Russian, but also in foreign markets — said General Director of CHEP Jaroslav wait.

During the construction and commissioning of the mini-mill company CHEP not only invested a record for such a facility in the technologies and measures to protect the environment, but also implemented a number of voluntary commitments on landscaping, renovation of schools, etc. At all stages of the construction and Launch Complex Company conducted an active dialogue with the public and local residents.

In operation, the complex the company will continue to pursue a responsible environmental policy and engage in dialogue with the public, — said Sergey Chikalov, technical director of CHEP.

Our company is interested in the development of Pervouralsk programs in different areas of city life: the environment, social services, education and sports. Stable operating company and key projects allow us to continue the existing projects and support new initiatives — said Jaroslav wait.

-Mill "Iron Ozone 32" of CTRP is one of the most technologically advanced production of metallurgical complex in Russia. The production plan for the current year is about 900,000 tons of continuously round billets. Launch complex will create 400 modern jobs and increase tax deductions at all levels of the budget by 600 million rubles annually.

-Mill "Iron Ozone 32"

ESPK of CTRP — one of the most technologically advanced production of metallurgical complex in Russia. The total cost of the project — more than $ 700 million

Associating the name of the shop — "Iron Ozone 32" — symbolizes the future of production, established on the basis of innovative technologies.

The complex will provide businesses of CHEP high quality, meeting all the standards and requirements of the workpiece for the production of seamless pipes. The manufacturing process of steel ESPK pretty simple. The production cycle takes less than an hour. Everything is automated, the minimum number of people on the site and no manual labor. By the way, gas treatment facilities in ESPK also a new generation. They can capture 99.9% produced during steelmaking process gases. Around the perimeter of the plant installed gas-and dust-collecting probes, the dust is subject to multiple cleaning gases "afterburned" to secure a post-combustion chamber, where the sensors are installed for monitoring of emissions. This allows you to continuously monitor the real-time performance scrubbing and instantly optimize the technology of smelting.

As in other "white" projects of each service-mill "Iron Ozone 32" its individual color: orange, red, black, or gray and white. Comfortable working conditions in the "white metal" is also provided with a high level of automation ESPK that lets you control units, the process and the production scale of the complex.

Collective’s "Iron Ozone" — is mostly skilled workers with higher education and language skills. On the "Iron Ozone 32" organized by the constant cycle of training for all units. Repair workers, steel workers, technicians studied the work of similar facilities in Germany, China, Italy, the Czech Republic, Mexico and Slovenia. It is with such a professional and cohesive team, mini-mill will be one of the most productive in Russia. Almost a million tons of steel a year will be able to produce just over 300 people. One worker will produce 3,400 tons of steel per year, which is three times more than the average steel plant in Russia.

Scale Construction
— The area of the complex is 80,000 square meters — that’s 16 football fields (shop area — 50,000 square meters).
— Only in the construction of EAF employs more than 20 contractors, whose work has been organized in two shifts. At the same time worked at the site of more than 2,000 construction workers, a day involved more than 100 vehicles.
— The scale of the entire complex, in fact, impressive. It took 90 thousand cubic meters of reinforced concrete and 12 tons of steel (1.5 Eiffel Tower), and the length of 714 kilometers of utilities

A high level of training ESPK iinovatsionny provides educational center of the company, built in Pervouralsk in 2011. Training center of international standards of education, and teaching laboratories equipped with leading technology companies in the world, is the venue for the Russian stage of the World Olympiad professional skills WorldSkills.

During the signing of the documents on the launch ESPK "Iron Ozone 32" PNTZ plant has reported on the implementation of the recommendations of oversight bodies and the public examinations under construction ESPK "Iron Ozone 32".

The cost of measures to protect the environment in connection with the construction ESPK "Iron Ozone 32" was about 1 billion rubles.

Pervouralsk New Pipe Plant (included in the company CTRP) completed the commissioning of the mini-mill "Iron Ozone 32".

The company completed the construction of CTRP-mill in November 2010. "Iron Ozone 32" — one of the largest investment projects in the domestic industry and the Sverdlovsk region. The volume of investments — about 19 billion rubles, of which about 1 billion was directed to an environmental dimension.

May 4, 2012 the head of the city district administration Pervoural’sk Yuri Pereversev signed authorization for commissioning electric arc PATH "Iron Ozone 32". 

The technologies used ESPK will produce steel billets for pipes manufactured in accordance with the most stringent national and international quality standards and deliver the products not only Russian, but also in foreign markets — said General Director of CHEP Jaroslav wait.

During the construction and commissioning of the mini-mill company CHEP not only invested a record for such a facility in the technologies and measures to protect the environment, but also implemented a number of voluntary commitments on landscaping, renovation of schools, etc. At all stages of the construction and Launch Complex Company conducted an active dialogue with the public and local residents.

In operation, the complex the company will continue to pursue a responsible environmental policy and engage in dialogue with the public, — said Sergey Chikalov, technical director of CHEP.

Our company is interested in the development of Pervouralsk programs in different areas of city life: the environment, social services, education and sports. Stable operating company and key projects allow us to continue the existing projects and support new initiatives — said Jaroslav wait.

-Mill "Iron Ozone 32" of CTRP is one of the most technologically advanced production of metallurgical complex in Russia. The production plan for the current year is about 900,000 tons of continuously round billets. Launch complex will create 400 modern jobs and increase tax deductions at all levels of the budget by 600 million rubles annually.

-Mill "Iron Ozone 32"

ESPK of CTRP — one of the most technologically advanced production of metallurgical complex in Russia. The total cost of the project — more than $ 700 million

Associating the name of the shop — "Iron Ozone 32" — symbolizes the future of production, established on the basis of innovative technologies.

The complex will provide businesses of CHEP high quality, meeting all the standards and requirements of the workpiece for the production of seamless pipes. The manufacturing process of steel ESPK pretty simple. The production cycle takes less than an hour. Everything is automated, the minimum number of people on the site and no manual labor. By the way, gas treatment facilities in ESPK also a new generation. They can capture 99.9% produced during steelmaking process gases. Around the perimeter of the plant installed gas-and dust-collecting probes, the dust is subject to multiple cleaning gases "afterburned" to secure a post-combustion chamber, where the sensors are installed for monitoring of emissions. This allows you to continuously monitor the real-time performance scrubbing and instantly optimize the technology of smelting.

As in other "white" projects of each service-mill "Iron Ozone 32" its individual color: orange, red, black, or gray and white. Comfortable working conditions in the "white metal" is also provided with a high level of automation ESPK that lets you control units, the process and the production scale of the complex.

Collective’s "Iron Ozone" — is mostly skilled workers with higher education and language skills. On the "Iron Ozone 32" organized by the constant cycle of training for all units. Repair workers, steel workers, technicians studied the work of similar facilities in Germany, China, Italy, the Czech Republic, Mexico and Slovenia. It is with such a professional and cohesive team, mini-mill will be one of the most productive in Russia. Almost a million tons of steel a year will be able to produce just over 300 people. One worker will produce 3,400 tons of steel per year, which is three times more than the average steel plant in Russia.

Scale Construction
— The area of the complex is 80,000 square meters — that’s 16 football fields (shop area — 50,000 square meters).
— Only in the construction of EAF employs more than 20 contractors, whose work has been organized in two shifts. At the same time worked at the site of more than 2,000 construction workers, a day involved more than 100 vehicles.
— The scale of the entire complex, in fact, impressive. It took 90 thousand cubic meters of reinforced concrete and 12 tons of steel (1.5 Eiffel Tower), and the length of 714 kilometers of utilities

A high level of training ESPK iinovatsionny provides educational center of the company, built in Pervouralsk in 2011. Training center of international standards of education, and teaching laboratories equipped with leading technology companies in the world, is the venue for the Russian stage of the World Olympiad professional skills WorldSkills.

During the signing of the documents on the launch ESPK "Iron Ozone 32" PNTZ plant has reported on the implementation of the recommendations of oversight bodies and the public examinations under construction ESPK "Iron Ozone 32".

The cost of measures to protect the environment in connection with the construction ESPK "Iron Ozone 32" was about 1 billion rubles.

 

  

 

  

 

 

 

 

 

 

 

 