Perezavedena for new equipment of 35 kV Naro-Fominsk —

Sludin-2 "in the west suburbs

 

Ltd. "Vympelsetstroy" (GC "Vympel") during the reconstruction works of 110/35/10 kV "Naro-Fominsk" carried out installation work upon replacement of an overhead transmission line (VL) 35 kV "Naro-Fominsk — Sludin-2" to the new equipment.

Customer construction works — OJSC "Moscow United Electric Grid."

According to the Deputy Technical Director of "Vympelsetstroy" Alexei Shiloh, "in accordance with the schedule, work continues upon replacement of 35 kV" Naro-Fominsk — Sludin-1. " Work is underway on the construction of outdoor switchgear (ORU) of 110 kV, and the commissioning of two new power transformers to 63 MVA. All work on upgrading power facility are carried out without disconnecting customers. "

Recall that in the course of the reconstruction of the feeding center Energostroitel completed the construction of the building switchgear closed in a modular design (KRUM) 35 kV. Ongoing construction of building of substation control (GTC) and the closed distribution system (ISG) 10 kV. Performed commissioning of four 110 kV gas-insulated circuit breakers.

To improve the accuracy of accounting transmit electricity supply center will be equipped with an automated information system for measurement of electricity (AMR). Through the use of an automated process control system (PCS) control service the customer will be able to perform operation control equipment remotely.