Power Machines fabricated, tested and handed over to the customer for a steam turbine CHP-3 Karaganda (Kazakhstan)

OJSC "Power Machines" manufactured, tested and delivered to the customer a steam turbine, designed for the new power Karaganda plant 3.

The contract for the manufacture and supply of equipment for the building under the fifth power of 150 MW was signed with Kazakhstan LLP "Karaganda Power Center" in June 2010.

In accordance with the terms of the contract "Power Machines" manufacture and supply at the plant steam turbine T-120/140-12, 8, and 160 MW turbine generator complete with excitation system, as well as auxiliary equipment of turbine. In addition, the specialists of "Power Machines" will provide services for installation supervision, commissioning and customer training. Completion of the delivery of equipment — the summer of 2011.

Earlier, in March this year, "Power Machines" ahead of the contractual terms of manufactured, tested and handed over to the customer for the Karaganda turbine generator plant.

New equipment is being built to the fifth power of the Karaganda CHP-3, is to be commissioned in 2011.

Participation in the project "Power Machines" — the continuation of cooperation of Russian power with the Kazakh energy sector. Earlier, in 2008, "Power Machines" produced and delivered to the power plant "Kazakhmys Corporation" steam turbine K-55-90-63 turbo T3FP.