Power Machines manufactured turbine generator for Belovo

"Power Machines" manufactured and tested the turbine of 220 MW for the sixth unit Belovo Siberian Generating Company (SGC).

 

The contract for the manufacture and supply of two turbines of 225 MW each, complete with turbo-generators for the modernization of Belovskaya power plant was signed by the parties in December 2010. Under the contract, "Power Machines" is not only manufacture and deliver turbine, turbine generators and ancillary equipment to the station, but also to perform the services of construction supervision and supervision of commissioning of equipment.

Siberian Generating Company is working on the replacement of two turbines at Belovo under the contract for the supply of power (PDM). As a result of their implementation at Units 4 and number 6 will be replaced or discarded turbines with a total installed capacity of 400 MW.

Commissioning of the unit number 4 is scheduled for December 2013, unit number 6 — at the end of 2014. The upgrade will increase the reliability of the station, as well as to increase the production of electrical energy required for the further development of the region.

In 2012, "Power Machines" produced complete 220 MW turbine generator with auxiliary equipment and a steam turbine with a capacity of 225 MW for the block number 4 Belovo. Currently, the production sites of "Power Machines", work is continuing on making the second turbine. Completion of the equipment is scheduled for delivery in June 2013.

Apart from the two turbines to Belovo "Power Machines" will manufacture equipment for the implementation of investment projects on two more stations SGK — Tom-Usinsk GRES and Kuznetsk CHP. All work on the manufacture and supply of turbines for these stations "Power machines" should be completed by June 1, 2013. Currently, the data power plants have already begun assembling the first set of turbine.