Power Machines produced the first turbine for the Leningrad NPP-2


 Photo source:power-m.ru

September 28. OJSC "Power Machines" manufactured and factory tests conducted on barring gear high-speed turbine capacity of 1,200 MW, designed for the first power Leningrad NPP-2 (LAES-2).

Contracts to supply a set of basic equipment to equip the machine room Novovoronezh NPP-2 (NV NPP-2) and Leningrad NPP-2 were signed between "Power Machines" and OAO "Atomenergoprom" in May 2008. The total contract value is more than 40 billion rubles. At each nuclear power plant will be built on two power units with VVER power capacity of 1,200 MW.

Earlier, in December 2010, "Power Machines" fabricated and tested a prototype model of turbine capacity of 1,200 MW for the first block NV NPP-2, and in May of this year for the same station after a successful trial has been handed over to the customer with a full-speed turbo water-cooled power 1,200 MW.

Closing shipment of the first turbine for NV NPP-2 and the beginning of the first shipment of turbines for NPP-2 is scheduled for the fourth quarter of 2011.

Speed steam turbines and turbo-generators with capacity of 1,200 MW of nuclear power — this innovative new design of "Power Machines", focused on a new generation of nuclear power units with enhanced reliability and security that are created in the Russian Federation in the framework of the "NPP-2006".

In the design and manufacture of high-speed steam turbines K-1200-6, 8/50 used new designs and technologies, taking into account the experience of designing and manufacturing turbines for nuclear power plants "Kudankulam" in India, "Bushehr" NPP in Iran and operation of turbines at the plant "Tianwan "in China.

Under the terms of the contracts "Power Machines" in the first stage provide the design, manufacture and supply of power for the first NV NPP-2 and Leningrad NPP-2 two sets of steam turbines, condensers and auxiliary equipment for the individual turbine systems, as well as two sets of turbine generators with equipment support systems, excitation system and the agent. Also "Power Machines" as a complete supplier of heat transfer equipment and deliver turbine pumps, pipelines and piping necessary fittings. In addition, power engineering company will carry out supervision inspection for assembly and start-up works at the nuclear power plant sites around the supplied equipment.

At the second stage of the "Power Machines" will ensure the supply of similar equipment and services for the second power NVNPP-2 and Leningrad NPP-2.

NV NPP-2 and Leningrad NPP-2 — is the first nuclear power plant to be built in Russia "from scratch" in the past 15 years.