Power Machines produced Urengoyskaya turbine generator for power plant (JSC OGK-1)

OJSC "Power Machines" ahead of the contractual terms of manufactured, tested and delivered to the customer turbine generator designed to Urengoyskaya built on the combined cycle power plant with a capacity of 450 MW (CCP-450).

In accordance with the terms of the agreement concluded in 2009 with JSC "OGK-1" and transferred in 2010 to the General Contractor — JSC "VO" Tekhnopromexport "," Power machines "made a steam turbine K-160-7, 5 and turbo type T3FP capacity of 160 MW, complete with excitation system. Currently, the "Power Machines" continue to manufacture steam turbines, the shipment of which is scheduled for November 2011.

Previously, under construction Urengoyskaya CCGT power plant "Power Machines" produced two gas turbine GTE-160 with capacity of 160 MW each, complete with air intake paths and automatic start-up and management.