Red Boiler concluded the shipment of equipment to Kursk


 Photo source:sdelanounas.ru

Taganrog Boiler Plant "Red Boiler" (the main production site of "EMA") has shipped the last sixth body PN-1800 for Kursk weighing 17.1 tons
The contract for the supply of products between OJSC "EMA" and signed by the customer in October 2010. As part of the agreement, "EMA" committed to complete the project and put the case of low pressure heaters PN-1800 for Kursk.
This equipment is intended to replace carbon steel body of existing low-pressure heaters Kursk. New stainless steel body type 08H18N10T made "Red boilermaker," have a high erosion and corrosion resistance, which in turn can significantly increase the reliability of both the equipment and the plant as a whole.
Recall that PN-1800 are designed to preheat the feed water recovery system of low pressure turbine nuclear power plant reactors of the RBMK-1000. All cases PN-1800 are designed to meet existing regulatory and technical documents and fully comply with the safety requirements for nuclear power plants.

Like this post? Please share to your friends: