Red Boiler manufacture equipment for power Bereza power plant under a contract worth more than 4 billion rubles.

SCC of "Red Boiler" (production site of "EMA", Rostov region). Manufacture equipment for the unit number 3 under construction Bereza power plant as part of a prisoner with JSC "Energoprojekt" contract worth more than 4 billion rubles. The press service of the company.


 Photo source:tkz.su

As part of the agreement, "EMA" will modernize and execute resupply and recovery IRREPARABLY operation of boiler equipment due to its long-term storage, as well as its partial replacement in accordance with the stringent environmental requirements. Thus, the "EMA" will supply power to the boiler plant for supercritical steam parameters. The total installed capacity of 800 MW of power. The installed capacity of Bereza power plant after the implementation of the project will be 2400 MW.
Work under this contract will be performed by specialists Podolski branch of "EMA". The main equipment for the project will be manufactured at the production site of "EMA" — SCC of "Red boilermaker."
The determining factors in choosing a design unit at supercritical steam parameters was to increase operational capabilities, environmental, technical and economic performance of the unit. Commissioning of the equipment of the power production number 3 "EMA" will not only significantly reduce emissions of nitrogen oxides to 300 mg / Nm? (Which corresponds to the most stringent Russian environmental requirements), but also completely eliminate the screens slagging combustor.
It should be noted that the construction of the block number 3 Bereza power plant is the largest project for the unit capacity of the coal energy constructed in accordance with the Order of the Government of the Russian Federation "List of generating facilities with which to implement the power supply under contracts for supply of power."
The planned duration of the project — the second quarter of 2013