The Krasnodar CHP produced a cold start of a new turbine power plants

The Krasnodar CHP on Friday, September 9 produced a "cold start" gas turbine M701F, which is part of the new power unit PGU-410 MW. At launch, attended by representatives of the Japanese corporation Mitsubishi Heavy Industries (MHI), as well as specialists of the general contractor of "E4 Group".


 Photo source:so-ups.ru

Commissioning of PGU-410 MW will: a 50% increase in the installed electrical capacity of the Krasnodar CHP, a 25% reduction in specific fuel consumption for electricity lets go, to ensure high reliability and operational efficiencies without sacrificing the impact on the environment.

"Cold start" is the initial stage of the start-up of the gas turbine and is in the supply voltage of the thyristor trigger on the turbine generator. A gas turbine generator in a motor mode, a common shaft line, transmits rotation to the compressor of the gas turbine speed rises to 700-800 rpm, providing the required flow rate and air pressure venting gas path and subsequent ignition of the gas in the primary combustion chambers.

"We are pleased with the results. Pre-start training cycle plant is in full swing. In the near future we plan to implement the ceremonial start of the object ", — Said the general director of "LUKOIL-Kubanenergo" Ilgiz GAREEV, the press service quoted.

Construc new unit built since 2008 Project cost 16 billion rubles, the payback period of 9 years. OOO "LUKOIL-Kubanenergo" is 100% owned by OAO "LUKOIL", created in 2009 during the reorganization of TGK-8 has a power and heat generating facilities located in Krasnodar. The structure of "LUKOIL-Kubanenergo" is the Krasnodar CHP. The total installed electric power utilities, LLC "LUKOIL-Kubanenergo" is 744 MW of installed thermal capacity of 781 Gcal / h